Myanmar - Rural Electrification Programme Component I SHS (REP I)
In the framework of the Rural Electrification Programme - Component I SHS (REP I), financed by the Federal Republic of Germany through KfW, the development objective of the project is to improve the access to clean and sustainable energy for the rural population in three districts of the Southern Shan State aiming at supporting the implementation of the National Electrification Plan of the Government of Myanmar.
The main objectives of the activities under this project are to:
- support the client (DRD) in the successful implementation of the programme
- strengthen and institutionalise DRD’s capacity to promote sustainable, off-grid electrification in rural areas through renewable energy sources
Important success factors of the programme are, among others: (1) 23,000 households have access to electricity at least four hours per day in 2022; (2) Solar systems produce at least 1.8 GWh/a in 2022; (3) support in setting up a sustainable battery recycling system as of 2022.
intec's services
- Inception, design and implementation planning
- Support during procurement and tender: development of technical specifications on bases of high quality Solar Home Systems (SHS), environmental & social management plan, preparation of bidding documents and evaluation of bids and contract negotiations.
- Capacity building, training and workshops for DRD and suppliers and installation companies
- Monitoring and supervision during project implementation in line with World Banks environmental and social standards.
- Coordination between the separately contracted Battery-Recycling Experts and DRD
- Coordination of all implementation activities with DRD, World Bank, GIZ and MoEE
- Economic and financial analysis
- Support during the disbursement procedure as per KfW guidelines and verification of withdrawal applications.
Client
Ministry of Agriculture, Livestock and IrrigationFinancing
KfW Development BankPeriod of implementation
1/2018 - 12/2020 -
Zimbabwe - Environmental and Social Impact Assessment (ESIA)
The Government of the Republic of Zimbabwe (GoZ) has received Grant funding from the African Development Fund (ADF) and intends to apply part of the proceeds of this Grant to eligible payments under the contract for preparing Environmental and Social Impact Assessment (ESIA) package reports for the following projects:
- Haven-Gokwe 132kV transmission line and Gokwe132/33kV substation;
- Tokwe–Masvingo 132kV transmission line and Masvingo 132/33kV substation; and
- Sunway City - Dema 132kV transmission line and Sunway City 132/33kV substation
Our task is production of comprehensive ESIA reports which meet the requirements of both the Environmental Management Agency (EMA) and the African Development Bank (AfDB) for the abovementioned proposed projects
intec's services
- Review and update the existing ESIA reports for the projects and align them to the format and standard required by (EMA) and AfDB
- Identify, assess and rank potential environmental and social impacts of the projects, filling in information/data gaps that exist in the current reports in terms of the biophysical, socio-economic and cultural and heritage sections
- Identify all potential significant adverse environmental and social impacts of the projects and recommend measures for mitigation;
- Incorporate: gender issues in the project area, climate change issues, environmental aspects and hazards in the project areas and how they can affect the transmission lines, cumulative and residual impacts associated with the projects ;
- Prepare an an Environmental and Social Impact Assessment (ESIA), an Environmental and Social Management Plan (ESMP), and a Resettlement Action Plan (RAP) for each of the projects in line with national requirements as well as those of the African Development Bank Groups ISS Policy Statement and Operational Procedures
Client
Zimbabwe Electricity Transmission and Distribution Company - ZETDCFinancing
African Development Bank (AfDB)Period of implementation
08.2019 – 01.2020 -
Guinea - Implementation of the National Dispatching
The general objective of this project is the monitoring and control of costs, of the quality and the time schedule of implementation works. The project includes all site works for the the National Dispatching Centre implementation. Following EDG's long-term master plan, the National Dispatching Centre shall integrate transmission lines at the level of 60 and 110 kV. The project has been interrupted due to the Ebola epidemic and new financing.
intec's services
- Coordination of activities between the Client EDG and the Contractor
- Check and approval of the Contractor's design and drawings during works execution
- Control of equipment manufacture
- Factory acceptance tests for main equipment
- Monthly / quarterly planning of project activities
- Control of works progress and adherence to the time schedule
- Coordination of meetings and drafting of Minutes of Meetings
- Monitoring of cost and implementation schedule
- Information to the Client about the progress of works and about any difficulties that could hamper smooth project implementation
- Elaboration of periodic progress reports
- Recommendation of necessary intervention measures to the Project Implementation Unit
- Validation of testing and commissioning procedures
- Proposals for settlement of accounts, preliminary and final taking over of works
Client
Electricité de Guinée (EDG)Financing
National Development Budget, Abu Dhabi Fund for Development (ADFD)Period of implementation
05.2014 - 12.2019
Myanmar - Rural Electrification Programme Component I SHS (REP I)
In the framework of the Rural Electrification Programme - Component I SHS (REP I), financed by the Federal Republic of Germany through KfW, the development objective of the project is to improve the access to clean and sustainable energy for the rural population in three districts of the Southern Shan State aiming at supporting the implementation of the National Electrification Plan of the Government of Myanmar.
The main objectives of the activities under this project are to:
- support the client (DRD) in the successful implementation of the programme
- strengthen and institutionalise DRD’s capacity to promote sustainable, off-grid electrification in rural areas through renewable energy sources
Important success factors of the programme are, among others: (1) 23,000 households have access to electricity at least four hours per day in 2022; (2) Solar systems produce at least 1.8 GWh/a in 2022; (3) support in setting up a sustainable battery recycling system as of 2022.
intec's services
- Inception, design and implementation planning
- Support during procurement and tender: development of technical specifications on bases of high quality Solar Home Systems (SHS), environmental & social management plan, preparation of bidding documents and evaluation of bids and contract negotiations.
- Capacity building, training and workshops for DRD and suppliers and installation companies
- Monitoring and supervision during project implementation in line with World Banks environmental and social standards.
- Coordination between the separately contracted Battery-Recycling Experts and DRD
- Coordination of all implementation activities with DRD, World Bank, GIZ and MoEE
- Economic and financial analysis
- Support during the disbursement procedure as per KfW guidelines and verification of withdrawal applications.
Client
Ministry of Agriculture, Livestock and IrrigationFinancing
KfW Development BankPeriod of implementation
1/2018 - 12/2020Zimbabwe - Environmental and Social Impact Assessment (ESIA)
The Government of the Republic of Zimbabwe (GoZ) has received Grant funding from the African Development Fund (ADF) and intends to apply part of the proceeds of this Grant to eligible payments under the contract for preparing Environmental and Social Impact Assessment (ESIA) package reports for the following projects:
- Haven-Gokwe 132kV transmission line and Gokwe132/33kV substation;
- Tokwe–Masvingo 132kV transmission line and Masvingo 132/33kV substation; and
- Sunway City - Dema 132kV transmission line and Sunway City 132/33kV substation
Our task is production of comprehensive ESIA reports which meet the requirements of both the Environmental Management Agency (EMA) and the African Development Bank (AfDB) for the abovementioned proposed projects
intec's services
- Review and update the existing ESIA reports for the projects and align them to the format and standard required by (EMA) and AfDB
- Identify, assess and rank potential environmental and social impacts of the projects, filling in information/data gaps that exist in the current reports in terms of the biophysical, socio-economic and cultural and heritage sections
- Identify all potential significant adverse environmental and social impacts of the projects and recommend measures for mitigation;
- Incorporate: gender issues in the project area, climate change issues, environmental aspects and hazards in the project areas and how they can affect the transmission lines, cumulative and residual impacts associated with the projects ;
- Prepare an an Environmental and Social Impact Assessment (ESIA), an Environmental and Social Management Plan (ESMP), and a Resettlement Action Plan (RAP) for each of the projects in line with national requirements as well as those of the African Development Bank Groups ISS Policy Statement and Operational Procedures
Client
Zimbabwe Electricity Transmission and Distribution Company - ZETDCFinancing
African Development Bank (AfDB)Period of implementation
08.2019 – 01.2020Guinea - Implementation of the National Dispatching
The general objective of this project is the monitoring and control of costs, of the quality and the time schedule of implementation works. The project includes all site works for the the National Dispatching Centre implementation. Following EDG's long-term master plan, the National Dispatching Centre shall integrate transmission lines at the level of 60 and 110 kV. The project has been interrupted due to the Ebola epidemic and new financing.
intec's services
- Coordination of activities between the Client EDG and the Contractor
- Check and approval of the Contractor's design and drawings during works execution
- Control of equipment manufacture
- Factory acceptance tests for main equipment
- Monthly / quarterly planning of project activities
- Control of works progress and adherence to the time schedule
- Coordination of meetings and drafting of Minutes of Meetings
- Monitoring of cost and implementation schedule
- Information to the Client about the progress of works and about any difficulties that could hamper smooth project implementation
- Elaboration of periodic progress reports
- Recommendation of necessary intervention measures to the Project Implementation Unit
- Validation of testing and commissioning procedures
- Proposals for settlement of accounts, preliminary and final taking over of works
Client
Electricité de Guinée (EDG)Financing
National Development Budget, Abu Dhabi Fund for Development (ADFD)Period of implementation
05.2014 - 12.2019-
Georgia - 220 kV Overhead Transmission Line Akhaltsikhe - Batumi
Georgian State Electrosystem JSC (GSE) is undertaking the 'Transmission Grid Strengthening Project' which includes measures to improve the availability and reliability of GSE's transmission infrastructure. The present project is part of this overall programme.
The line is constructed to connect the 185 MW Shuakhevi and the 150 MW Koromkheti Hydropower Stations to the national grid. It will have a length of approx. 150 km.
intec's services
- Overall project management and supervision
- Review and approval of detailed design
- Supervision of construction, erection, testing and commissioning
- Assistance to the Client in ensuring the compliance of land acquisition and resettlement activities with applicable laws and regulations (RAPs)
- Monitoring of compliance with the World Bank's environmental and social safeguards and the national Georgian legislation (ESIA, EMMP)
- Verification and approval of Contractor's invoices
- Reporting to the Client
- Capacity building for Client's personnel
Client
Georgian State Electrosystem JSCFinancing
International Bank for Reconstruction and Development (IBRD)Period of implementation
2015 - 2019 -
Serbia - Čibuk 1 Wind Farm Project
Vetroelecktrane is developing and executing, together with their major shareholders Abu Dhabi Future Energy Company-Masdar and Continental Wind Partners (CWP), a wind farm consisting of 57 Wind Turbine Generators (WTGs) of 110m hub height and 2.8 MW rated power, 86 km 35 kV cables, main transformer station (35 kV/400 kV; 2x 90 MVA), 11 km double circuit 400 kV OHL and corresponding infrastructure. The consultant has been appointed by the client to manage the project as owner's engineer, providing Project Management Consulting Services (PMC) and site supervision services (including design review, procurement, construction supervision, commissioning, start-up and testing) as well as technical advice and support during negotiations with third parties. The scope includes the following work packages:
- Work Package 2a: Engineering Services
- Work Package 2b: Construction Management and Site Supervision
- EDMS: Electronic Document Management Services
intec's services
- Establish project and document management structures
- Provide technical assistance to the client with any local authorities or other stakeholders.
- Review the design and engineering works carried out by the EPC contractor
- Contribute to the risk assessment (RA)
- Constructability review with the EPC contractors and other stakeholders
- EPC and project documentation review
- Performance of project controls (quality, cost and schedule, document, reporting, testing, factory inspection, health & safety, environmental, site inspection)
- Review of the contractor´s plan for site management and site supervision
- Performance of all health and safety activities prescribed by the Serbian law
- Provide assistance with maintaining compliance with EBRD and IFC requirements
- Supervision of all activities in relation to the connection to the utility network and services performed in relation to the Environmental Management Plan
Client
Vetroelecktrane Balcana (VEBG) D.O.OFinancing
Vetroelecktrane Balcana (VEBG) D.O.OPeriod of implementation
15.03.2017 - 30.11.2019 -
Moldova - Construction of 400 kV Vulcanesti - Chisinau Overhead Transmission Line
The project included the construction of the 400 kV transmission line connecting Vulcanesti Substation to Chisinau Substation and upgrading of the Chisinau and Vulcanesti Substations.
- The existing 330/110/35 kV Chisinau S/S was extended by a new 330 kV bay pertaining to 400/330 kV autotransformer and a new 400 kV bay for OHTL Vulcanesti - Chisinau.
- The 400 kV OHTL Vulcanesti - Chisinau with a length of 157 km, was made on single circuit towers, equipped with three bundle conductors and two earthwires, from which one is of OPGW type to permit optical transmission data.
The existing 400/110/35 kV Vulcanești Substation was extended by a new 400 kV bay for OHTL Vulcanești - Chisinau. In alternative, the OHTL will start from the new BtB Vulcanesti Station.
intec's services
- Review of the existing feasibility and other technical studies: review of proposed technical solutions and concept, identification of alternative line routes or tower locations, if required; preparation of a report to describe the proposed technical solutions and recommendations
- Preparation of preliminary design documents: detailed line routing and profiles, structural design of towers, fabrication and foundation drawings, clearance diagrams; single line diagrams and substation layouts; price schedules and technical data sheets
- Preparation of the bidding documents (World Bank procurement procedures) separately for the substations and the overhead line
Client
Moldova Energy Projects Implementation Unit (MEPIU)Financing
World Bank (WB)Period of implementation
03.2019 - 11.2019
Georgia - 220 kV Overhead Transmission Line Akhaltsikhe - Batumi
Georgian State Electrosystem JSC (GSE) is undertaking the 'Transmission Grid Strengthening Project' which includes measures to improve the availability and reliability of GSE's transmission infrastructure. The present project is part of this overall programme.
The line is constructed to connect the 185 MW Shuakhevi and the 150 MW Koromkheti Hydropower Stations to the national grid. It will have a length of approx. 150 km.
intec's services
- Overall project management and supervision
- Review and approval of detailed design
- Supervision of construction, erection, testing and commissioning
- Assistance to the Client in ensuring the compliance of land acquisition and resettlement activities with applicable laws and regulations (RAPs)
- Monitoring of compliance with the World Bank's environmental and social safeguards and the national Georgian legislation (ESIA, EMMP)
- Verification and approval of Contractor's invoices
- Reporting to the Client
- Capacity building for Client's personnel
Client
Georgian State Electrosystem JSCFinancing
International Bank for Reconstruction and Development (IBRD)Period of implementation
2015 - 2019Serbia - Čibuk 1 Wind Farm Project
Vetroelecktrane is developing and executing, together with their major shareholders Abu Dhabi Future Energy Company-Masdar and Continental Wind Partners (CWP), a wind farm consisting of 57 Wind Turbine Generators (WTGs) of 110m hub height and 2.8 MW rated power, 86 km 35 kV cables, main transformer station (35 kV/400 kV; 2x 90 MVA), 11 km double circuit 400 kV OHL and corresponding infrastructure. The consultant has been appointed by the client to manage the project as owner's engineer, providing Project Management Consulting Services (PMC) and site supervision services (including design review, procurement, construction supervision, commissioning, start-up and testing) as well as technical advice and support during negotiations with third parties. The scope includes the following work packages:
- Work Package 2a: Engineering Services
- Work Package 2b: Construction Management and Site Supervision
- EDMS: Electronic Document Management Services
intec's services
- Establish project and document management structures
- Provide technical assistance to the client with any local authorities or other stakeholders.
- Review the design and engineering works carried out by the EPC contractor
- Contribute to the risk assessment (RA)
- Constructability review with the EPC contractors and other stakeholders
- EPC and project documentation review
- Performance of project controls (quality, cost and schedule, document, reporting, testing, factory inspection, health & safety, environmental, site inspection)
- Review of the contractor´s plan for site management and site supervision
- Performance of all health and safety activities prescribed by the Serbian law
- Provide assistance with maintaining compliance with EBRD and IFC requirements
- Supervision of all activities in relation to the connection to the utility network and services performed in relation to the Environmental Management Plan
Client
Vetroelecktrane Balcana (VEBG) D.O.OFinancing
Vetroelecktrane Balcana (VEBG) D.O.OPeriod of implementation
15.03.2017 - 30.11.2019Moldova - Construction of 400 kV Vulcanesti - Chisinau Overhead Transmission Line
The project included the construction of the 400 kV transmission line connecting Vulcanesti Substation to Chisinau Substation and upgrading of the Chisinau and Vulcanesti Substations.
- The existing 330/110/35 kV Chisinau S/S was extended by a new 330 kV bay pertaining to 400/330 kV autotransformer and a new 400 kV bay for OHTL Vulcanesti - Chisinau.
- The 400 kV OHTL Vulcanesti - Chisinau with a length of 157 km, was made on single circuit towers, equipped with three bundle conductors and two earthwires, from which one is of OPGW type to permit optical transmission data.
The existing 400/110/35 kV Vulcanești Substation was extended by a new 400 kV bay for OHTL Vulcanești - Chisinau. In alternative, the OHTL will start from the new BtB Vulcanesti Station.
intec's services
- Review of the existing feasibility and other technical studies: review of proposed technical solutions and concept, identification of alternative line routes or tower locations, if required; preparation of a report to describe the proposed technical solutions and recommendations
- Preparation of preliminary design documents: detailed line routing and profiles, structural design of towers, fabrication and foundation drawings, clearance diagrams; single line diagrams and substation layouts; price schedules and technical data sheets
- Preparation of the bidding documents (World Bank procurement procedures) separately for the substations and the overhead line