Training & Capacity Building - Project examples
-
Rwanda - Capacity Building Programs and Technical Assistances to Strengthen the Energy Sector in Rwanda - "Scaling-up Energy Access Project"
To organize, provide and supervise a capacity building program (training, technical assistance, coaching, mentoring, etc.) for the energy sector in Rwanda, especially in the Ministry of Infrastructure (MININFRA), the Rwanda Energy Group (REG) and EARP (Electricity Access Roll-out Program PIU) to develop a strong sector management capacity (at individual, institutional and organizational level) and to improve these institutions’ investment planning, technical, operational, finance and support services functions. The capacity building programs will include advanced long-term, medium and short courses, which will be organized locally or abroad.
intec's services
- Capacity needs assessment of MININFRA, REG and EARP
- Organization, provision and supervision of an extensive training and capacity building program and provision of technical assistance.
Topics of the capacity building and training program include:
- Energy policy, strategy and management: Development of generation resource; renewable energy development; utility restructuring and best practice; regional projects and power pools; system operator and power trading; substation operation and maintenance; strategic planning and M&E,
- Energy development, investment and program implementation: Financial analysis, planning and modelling; bulk power generation and transmission network planning; investment planning and funding; IPP and PPPs, operations and management; asset management; project management; construction and contract management; procurement; environmental issues; monitoring and evaluation; project financial management; strategic maintenance planning, planning and design, GIS, load flows and load forecasting.
The technical assistance covers inter alia:
- Energy efficiency development programs; loss reduction in the electrical network; power trading; regional interconnection, energy planning strategy
Client
Energy Development Corporation Limited (EDCL)Financing
African Development Fund (AfDF)Period of implementation
2015 - 2017 -
ECOWAS - Reduction of Distribution Losses in the Framework of the GIZ Project "Promoting a Climate-Friendly Interconnected Power System in West Africa"
ECOWAS, the Economic Community of West African states comprises 15 West African countries: Benin, Burkina Faso, Cabo Verde, Côte d'Ivoire, Gambia, Ghana, Guinea, Guinea-Bissau, Liberia, Mali, Niger, Nigeria, Senegal, Sierra Leone and Togo. The overall GIZ project supports the regional dissemination of experience concerning renewable energies and aims at improving the capacities of utilities in the long term. The "electricity distribution" part of the project, together with selected utilities, identifies options for the reduction of distribution losses, implements exemplary measures and disseminates the results in the region.
intec's services
- Task 1: Data collection, review and analysis of current situation in the member utilities: Diagnosis on the prac-tices of loss reduction, catalogue of good practices, proposal of related initiatives/projects for each utility, ex-amination of the adequacy of existing master plans in the distribution utilities and proposal of required updates including costs
- Task 2: Study to quantify system losses: Determination of loss levels by utility, estimate of share of technical losses, preparation of mitigation measures, review of / proposal for energy audit system for each utility, preparation of indicative plans and targets for capital expenditure to reduce overall losses possibly to below 10%
- Task 3: Loss reduction investment plans and cost estimates: development and recommendation of a comprehensive short- and long-term loss reduction investment plan including costs, recommendation of technical measures such as norms, standards and loss management guidelines
- Task 4: Training and capacity building: training needs assessment of utility staff, recommendations for capacity building programs in line with WAPP's capacity building program for member utilities and in coordination with GIZ's capacity building activities of the overall project.
Client
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbHFinancing
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbHPeriod of implementation
04.2015 - 07.2017 -
Bangladesh - Feasibility Study of the Transmission System Improvement, Western Zone
Bangladesh faces chronic power shortage with an estimated demand gap in the magnitude of 1900 MW and power outages in urban areas between 5-10 hours a day. Taking into account the demand forecast(s), the current load shedding and the extreme power shortage and operational constraints, PGCB launched the "Power Transmission Improvement Programme" and approached the Government for external sector assistance.
The project covers the following technical measures:- Construction of 132 kV double-circuit transmission lines and line in-/line outs to substations
- Stringing of a second circuit on an existing 132 kV line and installation of OPGW
- Construction of 230 kV double-circuit transmission lines and line-in/line-out to existing lines
- New construction of three 132/33 kV and one 230/132 kV substation
- Extension of a total of five 132/33 kV and one 230/132 kV substation (1 GIS substation)
intec's services
Feasibility study/technical and economic justification of the planned expansion measures, i.e.:
- Network analysis and update of load flow calculations
- Assessment of socio-economic benefits
- Preliminary line route identification
- Preliminary survey of substation areas
- Layout and design on feasibility level for the 230 and 132 kV lines, substations and substation extensions
- Identification of potential training needs in terms of O&M
- Cost estimate, economic and financial analysis of planned measures
- Initial Environmental Examination (IEE) and mitigation measures
- Detailed line route survey for 70 km of 230 DC line and a total of 85 km of 132 DC lines
- Full ESIA for the selected technical measures to be implemented and Environmental and Social Management Plan (ESMP)
Tendering of resulting first-priority measures, i.e.:
- Design and elaboration of technical specifications
- Determination of the bills of quantities
- Preparation of the tender dossiers (technical and commercial)
- Assistance during tendering
- Bid evaluation
- Assistance during contract negotiations
in total for six different tender packages (three substation packages and three transmission line packages).
Client
Power Grid Company of Bangladesh Ltd. (PGCB)Financing
KfW EntwicklungsbankPeriod of implementation
01.2014 - 07.2017
Rwanda - Capacity Building Programs and Technical Assistances to Strengthen the Energy Sector in Rwanda - "Scaling-up Energy Access Project"
To organize, provide and supervise a capacity building program (training, technical assistance, coaching, mentoring, etc.) for the energy sector in Rwanda, especially in the Ministry of Infrastructure (MININFRA), the Rwanda Energy Group (REG) and EARP (Electricity Access Roll-out Program PIU) to develop a strong sector management capacity (at individual, institutional and organizational level) and to improve these institutions’ investment planning, technical, operational, finance and support services functions. The capacity building programs will include advanced long-term, medium and short courses, which will be organized locally or abroad.
intec's services
- Capacity needs assessment of MININFRA, REG and EARP
- Organization, provision and supervision of an extensive training and capacity building program and provision of technical assistance.
Topics of the capacity building and training program include:
- Energy policy, strategy and management: Development of generation resource; renewable energy development; utility restructuring and best practice; regional projects and power pools; system operator and power trading; substation operation and maintenance; strategic planning and M&E,
- Energy development, investment and program implementation: Financial analysis, planning and modelling; bulk power generation and transmission network planning; investment planning and funding; IPP and PPPs, operations and management; asset management; project management; construction and contract management; procurement; environmental issues; monitoring and evaluation; project financial management; strategic maintenance planning, planning and design, GIS, load flows and load forecasting.
The technical assistance covers inter alia:
- Energy efficiency development programs; loss reduction in the electrical network; power trading; regional interconnection, energy planning strategy
Client
Energy Development Corporation Limited (EDCL)Financing
African Development Fund (AfDF)Period of implementation
2015 - 2017ECOWAS - Reduction of Distribution Losses in the Framework of the GIZ Project "Promoting a Climate-Friendly Interconnected Power System in West Africa"
ECOWAS, the Economic Community of West African states comprises 15 West African countries: Benin, Burkina Faso, Cabo Verde, Côte d'Ivoire, Gambia, Ghana, Guinea, Guinea-Bissau, Liberia, Mali, Niger, Nigeria, Senegal, Sierra Leone and Togo. The overall GIZ project supports the regional dissemination of experience concerning renewable energies and aims at improving the capacities of utilities in the long term. The "electricity distribution" part of the project, together with selected utilities, identifies options for the reduction of distribution losses, implements exemplary measures and disseminates the results in the region.
intec's services
- Task 1: Data collection, review and analysis of current situation in the member utilities: Diagnosis on the prac-tices of loss reduction, catalogue of good practices, proposal of related initiatives/projects for each utility, ex-amination of the adequacy of existing master plans in the distribution utilities and proposal of required updates including costs
- Task 2: Study to quantify system losses: Determination of loss levels by utility, estimate of share of technical losses, preparation of mitigation measures, review of / proposal for energy audit system for each utility, preparation of indicative plans and targets for capital expenditure to reduce overall losses possibly to below 10%
- Task 3: Loss reduction investment plans and cost estimates: development and recommendation of a comprehensive short- and long-term loss reduction investment plan including costs, recommendation of technical measures such as norms, standards and loss management guidelines
- Task 4: Training and capacity building: training needs assessment of utility staff, recommendations for capacity building programs in line with WAPP's capacity building program for member utilities and in coordination with GIZ's capacity building activities of the overall project.
Client
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbHFinancing
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbHPeriod of implementation
04.2015 - 07.2017Bangladesh - Feasibility Study of the Transmission System Improvement, Western Zone
Bangladesh faces chronic power shortage with an estimated demand gap in the magnitude of 1900 MW and power outages in urban areas between 5-10 hours a day. Taking into account the demand forecast(s), the current load shedding and the extreme power shortage and operational constraints, PGCB launched the "Power Transmission Improvement Programme" and approached the Government for external sector assistance.
The project covers the following technical measures:
- Construction of 132 kV double-circuit transmission lines and line in-/line outs to substations
- Stringing of a second circuit on an existing 132 kV line and installation of OPGW
- Construction of 230 kV double-circuit transmission lines and line-in/line-out to existing lines
- New construction of three 132/33 kV and one 230/132 kV substation
- Extension of a total of five 132/33 kV and one 230/132 kV substation (1 GIS substation)
intec's services
Feasibility study/technical and economic justification of the planned expansion measures, i.e.:
- Network analysis and update of load flow calculations
- Assessment of socio-economic benefits
- Preliminary line route identification
- Preliminary survey of substation areas
- Layout and design on feasibility level for the 230 and 132 kV lines, substations and substation extensions
- Identification of potential training needs in terms of O&M
- Cost estimate, economic and financial analysis of planned measures
- Initial Environmental Examination (IEE) and mitigation measures
- Detailed line route survey for 70 km of 230 DC line and a total of 85 km of 132 DC lines
- Full ESIA for the selected technical measures to be implemented and Environmental and Social Management Plan (ESMP)
Tendering of resulting first-priority measures, i.e.:
- Design and elaboration of technical specifications
- Determination of the bills of quantities
- Preparation of the tender dossiers (technical and commercial)
- Assistance during tendering
- Bid evaluation
- Assistance during contract negotiations
in total for six different tender packages (three substation packages and three transmission line packages).
Client
Power Grid Company of Bangladesh Ltd. (PGCB)Financing
KfW EntwicklungsbankPeriod of implementation
01.2014 - 07.2017-
Rwanda, Burundi - Regional Interconnection Project (220 kV Transmission Line Kigoma - Butare - Ngozi - Gitega and 220/110 kV Substations)
The project was part of the NELSAP Regional Transmission Program that aimed at interconnecting five of the Nile Equatorial Lakes Countries, i.e. Burundi, DR Congo, Kenya, Rwanda and Uganda.
The project interconnected the electricity networks of Burundi and Rwanda through the construction of a new 220 kV single-circuit transmission line with a total length of 143 km. The line will initially be operated on the 110 kV level and might later be upgraded to 220 kV.
The project also included the construction of two new 220/110 kV substations, the extension of two existing 110 kV substations and the construction of 11.2 km of 30 kV line for rural electrification of Gisagara (Rwanda).
intec's services
- Review of existing feasibility studies
- Update of the Environmental and Social Management Plan (ESMP)
- Detailed design
- Preparation of complete tender documents for EPC Contractors (2 lots)
- Technical assistance during the procurement process, i.e. tendering, bid evaluation and contract award
- Preparation of a detailed Resettlement Action Plan (RAP) and monitoring of its implementation
- Design approval and supervision of implementation works
- Witnessing of factory acceptance tests, supervision of testing and commissioning
- Certification of Contractor's invoices and payments
- Monitoring and supervision of the implementation of the ESMP
- Safeguarding of project's compliance with KfW's and the World Bank's sustainability guidelines
- Technology transfer and training of employers' and project executing agency's staff
- Representation in the respective project steering and technical committees
Client
REGIDESO (Burundi), Energy Development Corporation Ltd. (Rwanda)Financing
KfW EntwicklungsbankPeriod of implementation
03.2015 - 06.2017 -
Mauritania - Construction of a 120 (180) MW dual-fuel power plant in Nouakchott
The state-owned utility SOMELEC is currently constructing a new power plant in Nouakchott to answer the steadily increasing power demand in the city and eventually in the national and international grid. This power plant, in its initial phase, had a capacity of 120 MW (8 x 15 MW dual-fuel gen sets, operated either with HFO or gas). In the second phase, the plant is currently extended to 180 MW capacity by adding a further four gen sets.
intec's services
- Choice of site for the power plant
- Review of the existing design report and preparation of tender documents
- Assistance to SOMELEC during tendering, tender evaluation, contract negotiation and contract conclusion
- Follow-up, coordination and control of design studies and manufacturing
- Supervision, monitoring and coordination of site works
- Verification of equipment lists
- Implementation of the training plan for the future operating personnel
- Preparation of tender documents for the power plant access road, follow-up, coordination and control of construction.
Client
SOMELEC - Mauritanian Electricity CompanyFinancing
Arab Fund for Economic and Social DevelopmentPeriod of implementation
08.2011 - 06.2017 -
Nigeria - Grid-Connected Solar Power Plant (Feasibility Study & Pre-Feasibility Studies)
In its Roadmap for Power Sector Reforms (2013), Nigeria has articulated its commitment to accelerate economic growth while reducing its GHG emissions, i.a. by introducing renewables to the energy mix. The present project shall contribute to this goal. It includes the following main tasks:
- an in-depth feasibility study including power system integration studies for the development of a 50 MW solar plant at a single site in the State of Bauchi, allowing for modular scale-up and phased development, intended to lead to an investment bid;
- a pre-feasibility study on possible cogeneration feeder plants (20-50 MW) adjacent to existing and upcoming hydropower plants (e.g. Shiro-ro, Jebba, Kainji), grid-connected, centralized and/or distributed, in-tended to lead to functional bids;
- a pre-feasibility study on possible embedded generation plants within privatised DISCOs, grid-connected or distributed, intended to lead to functional bids;
- the preparation of tender documents for EPC;
- a training and capacity building programme.
intec's services
For all three studies, the scope of work includes i.a.:
- site identification and screening
- determination of solar resource
- selection of two best-ranked sites on the basis of technical-economic analyses
- investigation of grid integration and topographical issues
- preparation of an environmental and social management framework
- development of an investment plan
- elaboration of technical concept for the PV plant and the interconnection to the grid
- sensitivity analyses, commercial considerations
- determination of optimum plant sizes and potential for future expansion
- selection of highest-ranked sites and preparation of concept note and design, preliminary topographical survey and geotechnical investigation
In addition, the in-depth feasibility study for the investment bid includes the following services:
- preparation of concept design, drawings, cost estimate and implementation schedule
- comparison of off-take options (bulk trader or sale to DISCO) and feasibility of interconnection policies
- environmental scoping for the selected sites and preparation of ToR for a full ESIA
- preparation of complete tender documents for EPC
- preparation of a deployment and a marketing plan
The pre-feasibility scoping studies have the following additional deliverables:
- investor profiling and ranking, investment and development timelines
- preparation of business plans
- configuration and specification of respective projects and their justification, identification of key milestones, activities, potential partners, etc.
- indicative options for possible ownership and financing (third-party PPA, owner-operated, hybrid financing, capital lease arrangements, etc.)
The project also includes an extensive training, capacity building and dissemination programme, which includes inter alia:
- Seminars and workshops in Abuja on
PV technology, PV project planning in the Nigerian context
Economic and financial analysis of PV power plants
PV power plant basic design, technical specifications, tender documents and ESIA- A one-week study tour to Germany: visits to large-scale PV power plants, research facilities, a regional dispatch centre, a manufacturer of PV modules, project developers, EPC Contractors, etc.
- On-the-job training along all project activities.
Client
Federal Ministry of the Environment, Nigeria Erosion and Watershed Management Project (NEWMAP)Financing
World BankPeriod of implementation
03.2015 - 03.2017
Rwanda, Burundi - Regional Interconnection Project (220 kV Transmission Line Kigoma - Butare - Ngozi - Gitega and 220/110 kV Substations)
The project was part of the NELSAP Regional Transmission Program that aimed at interconnecting five of the Nile Equatorial Lakes Countries, i.e. Burundi, DR Congo, Kenya, Rwanda and Uganda.
The project interconnected the electricity networks of Burundi and Rwanda through the construction of a new 220 kV single-circuit transmission line with a total length of 143 km. The line will initially be operated on the 110 kV level and might later be upgraded to 220 kV.
The project also included the construction of two new 220/110 kV substations, the extension of two existing 110 kV substations and the construction of 11.2 km of 30 kV line for rural electrification of Gisagara (Rwanda).
intec's services
- Review of existing feasibility studies
- Update of the Environmental and Social Management Plan (ESMP)
- Detailed design
- Preparation of complete tender documents for EPC Contractors (2 lots)
- Technical assistance during the procurement process, i.e. tendering, bid evaluation and contract award
- Preparation of a detailed Resettlement Action Plan (RAP) and monitoring of its implementation
- Design approval and supervision of implementation works
- Witnessing of factory acceptance tests, supervision of testing and commissioning
- Certification of Contractor's invoices and payments
- Monitoring and supervision of the implementation of the ESMP
- Safeguarding of project's compliance with KfW's and the World Bank's sustainability guidelines
- Technology transfer and training of employers' and project executing agency's staff
- Representation in the respective project steering and technical committees
Client
REGIDESO (Burundi), Energy Development Corporation Ltd. (Rwanda)Financing
KfW EntwicklungsbankPeriod of implementation
03.2015 - 06.2017Mauritania - Construction of a 120 (180) MW dual-fuel power plant in Nouakchott
The state-owned utility SOMELEC is currently constructing a new power plant in Nouakchott to answer the steadily increasing power demand in the city and eventually in the national and international grid. This power plant, in its initial phase, had a capacity of 120 MW (8 x 15 MW dual-fuel gen sets, operated either with HFO or gas). In the second phase, the plant is currently extended to 180 MW capacity by adding a further four gen sets.
intec's services
- Choice of site for the power plant
- Review of the existing design report and preparation of tender documents
- Assistance to SOMELEC during tendering, tender evaluation, contract negotiation and contract conclusion
- Follow-up, coordination and control of design studies and manufacturing
- Supervision, monitoring and coordination of site works
- Verification of equipment lists
- Implementation of the training plan for the future operating personnel
- Preparation of tender documents for the power plant access road, follow-up, coordination and control of construction.
Client
SOMELEC - Mauritanian Electricity CompanyFinancing
Arab Fund for Economic and Social DevelopmentPeriod of implementation
08.2011 - 06.2017Nigeria - Grid-Connected Solar Power Plant (Feasibility Study & Pre-Feasibility Studies)
In its Roadmap for Power Sector Reforms (2013), Nigeria has articulated its commitment to accelerate economic growth while reducing its GHG emissions, i.a. by introducing renewables to the energy mix. The present project shall contribute to this goal. It includes the following main tasks:
- an in-depth feasibility study including power system integration studies for the development of a 50 MW solar plant at a single site in the State of Bauchi, allowing for modular scale-up and phased development, intended to lead to an investment bid;
- a pre-feasibility study on possible cogeneration feeder plants (20-50 MW) adjacent to existing and upcoming hydropower plants (e.g. Shiro-ro, Jebba, Kainji), grid-connected, centralized and/or distributed, in-tended to lead to functional bids;
- a pre-feasibility study on possible embedded generation plants within privatised DISCOs, grid-connected or distributed, intended to lead to functional bids;
- the preparation of tender documents for EPC;
- a training and capacity building programme.
intec's services
For all three studies, the scope of work includes i.a.:
- site identification and screening
- determination of solar resource
- selection of two best-ranked sites on the basis of technical-economic analyses
- investigation of grid integration and topographical issues
- preparation of an environmental and social management framework
- development of an investment plan
- elaboration of technical concept for the PV plant and the interconnection to the grid
- sensitivity analyses, commercial considerations
- determination of optimum plant sizes and potential for future expansion
- selection of highest-ranked sites and preparation of concept note and design, preliminary topographical survey and geotechnical investigation
In addition, the in-depth feasibility study for the investment bid includes the following services:
- preparation of concept design, drawings, cost estimate and implementation schedule
- comparison of off-take options (bulk trader or sale to DISCO) and feasibility of interconnection policies
- environmental scoping for the selected sites and preparation of ToR for a full ESIA
- preparation of complete tender documents for EPC
- preparation of a deployment and a marketing plan
The pre-feasibility scoping studies have the following additional deliverables:
- investor profiling and ranking, investment and development timelines
- preparation of business plans
- configuration and specification of respective projects and their justification, identification of key milestones, activities, potential partners, etc.
- indicative options for possible ownership and financing (third-party PPA, owner-operated, hybrid financing, capital lease arrangements, etc.)
The project also includes an extensive training, capacity building and dissemination programme, which includes inter alia:
- Seminars and workshops in Abuja on
PV technology, PV project planning in the Nigerian context
Economic and financial analysis of PV power plants
PV power plant basic design, technical specifications, tender documents and ESIA
- A one-week study tour to Germany: visits to large-scale PV power plants, research facilities, a regional dispatch centre, a manufacturer of PV modules, project developers, EPC Contractors, etc.
- On-the-job training along all project activities.
Client
Federal Ministry of the Environment, Nigeria Erosion and Watershed Management Project (NEWMAP)Financing
World BankPeriod of implementation
03.2015 - 03.2017-
Uganda - Interconnection Code & Wheeling Agreement
The preparation of an interconnection code and a wheeling agreement is part of the GET FiT Uganda Program, launched in May 2013 to promote private investment into renewable energy generation projects in Uganda.
The main purpose of program is to fast-track a portfolio of about 20-25 small-scale renewable energy generation projects (promoted by private developers with a total installed capacity of roughly 150 MW). The overall objective of the present assignment is to enable proper and full evacuation of embedded generators in the future, at allowable national and international techno-economic standards.
The project includes detailed technical and economic requirements for connecting generation facilities to the existing grid and will involve both interconnection and wheeling aspects.
For this purpose, the following work packages constitute the framework of the project:
Part A - Work Package 1: Interconnection and Grid Code for fluctuating renewable energy power integration into the grid
Part B - Work Package 2: Wheeling Agreement for fluctuating renewable energy power wheeling
Part C - Work Package 3: Knowledge Transfer Programme.
intec's services
- Development of an interconnection code for fluctuating renewable based power integration based on technical, legal and commercial issues
- Development of a wheeling agreement for wheeling of fluctuating renewable power according to the current policy and regulatory framework
- Development and test of a model for the computation of wheeling losses
- Proposal for wheeler's grid availability performance guarantees and penalty measures for non-compliance
- Development of a knowledge transfer program
- Conducting two workshops on interconnection and wheeling issues.
Client
Electricity Regulatory Authority (ERA)Financing
KfW EntwicklungsbankPeriod of implementation
05.2016 - 01.2017 -
Guinea/Mali - 225 kV Interconnection Guinea - Mali
In order to accelerate the implementation of its priority projects, the West African Power Pool (WAPP), on behalf of EDG and EDM, commissioned this project to prepare the construction of an HV overhead line and associated substations from N'Zékéroré (Guinea) via Fomi (Guinea) to Bamako (Mali). The project includes a feasibility study and the preparation of prequalification/tender documents for the following installations:
- The construction of 714 km of 225 kV line
- The extension or new construction of six 225 kV substations in Guinea (N'Zérékoré, Fomi, Beyla, Kérouané, Kankan, Siguiri)
- Additionally, the construction of a new 225 kV substation in Sanankoroba, some 25 km west of Bamako (Mali)
intec's services
- Feasibility study
- Technical study of the interconnection, collection and analysis of data, system study/planning of integrating the new 225 kV line into WAPP's interconnected network (over a time span of 20 years of operation), preliminary design (line, substations, communication and SCADA systems), economic and financial analysis
- Preparation of the prequalification/tender documents and the required split of works into different lots
- Training programme/human resource development for the concerned electricity companies, energy ministries and for staff of the General Directorate of WAPP through training on the job and in the Consultant's home office
Client
West African Power Pool (WAPP) / Système d'Echange d'Energie Electrique Ouest Africain (EEEOA)Financing
African Development BankPeriod of implementation
01.2014 - 06.2016 -
Bangladesh - New 132/33 GIS Substations, a New Cable System and a 4-circuit 132 kV transmission line
The project shall contribute to the Sustainable Power Sector Development Program II by securing proper voltage levels, and thereby reducing transmission losses. This transmission system improvement is necessary to achieve a sustainable restructuring of the power sector. The project includes the following measures:
- Lot 1 - Substations: Construction of new 132/33 kV GIS substations at Lalbagh and Madertak, and conversion of 132/33 kV Dhanmodi transformer station into a regular substation, including construction of an additional 132 kV bay (one and a half breaker scheme) at Rampura Substation
- Lot 2 - Cable system: Construction of a new 132 and 33 kV underground cable system
- Lot 3 - Transmission lines: Construction of 4-circuit 132 kV overhead transmission lines including a river crossing
intec's services
- Assistance to PIU in bid evaluations then drafting the Notice of Award Recommendation
- Assistance in contract negotiations
- Control of Contractor's time schedule
- Assist contractor in obtaining permits and Wayleave Rights
- Approval of Contractor's/suppliers' design
- Participation in Factory Acceptance Tests (FATs)
- Approval of final design and as-built design
- Supervision of construction
- Budget control and invoice review
- Monitoring the training programme
- Assistance to PIU in establishing an operations and maintenance concept
- Assistance in commissioning and assistance during Defects Liability Period (DLP) and warranty period
Client
Dhaka Power Distribution Company Ltd. (DPDC)Financing
KfW EntwicklungsbankPeriod of implementation
06.2009 - 06.2016
Uganda - Interconnection Code & Wheeling Agreement
The preparation of an interconnection code and a wheeling agreement is part of the GET FiT Uganda Program, launched in May 2013 to promote private investment into renewable energy generation projects in Uganda.
The main purpose of program is to fast-track a portfolio of about 20-25 small-scale renewable energy generation projects (promoted by private developers with a total installed capacity of roughly 150 MW). The overall objective of the present assignment is to enable proper and full evacuation of embedded generators in the future, at allowable national and international techno-economic standards.
The project includes detailed technical and economic requirements for connecting generation facilities to the existing grid and will involve both interconnection and wheeling aspects.
For this purpose, the following work packages constitute the framework of the project:
Part A - Work Package 1: Interconnection and Grid Code for fluctuating renewable energy power integration into the grid
Part B - Work Package 2: Wheeling Agreement for fluctuating renewable energy power wheeling
Part C - Work Package 3: Knowledge Transfer Programme.
intec's services
- Development of an interconnection code for fluctuating renewable based power integration based on technical, legal and commercial issues
- Development of a wheeling agreement for wheeling of fluctuating renewable power according to the current policy and regulatory framework
- Development and test of a model for the computation of wheeling losses
- Proposal for wheeler's grid availability performance guarantees and penalty measures for non-compliance
- Development of a knowledge transfer program
- Conducting two workshops on interconnection and wheeling issues.
Client
Electricity Regulatory Authority (ERA)Financing
KfW EntwicklungsbankPeriod of implementation
05.2016 - 01.2017Guinea/Mali - 225 kV Interconnection Guinea - Mali
In order to accelerate the implementation of its priority projects, the West African Power Pool (WAPP), on behalf of EDG and EDM, commissioned this project to prepare the construction of an HV overhead line and associated substations from N'Zékéroré (Guinea) via Fomi (Guinea) to Bamako (Mali). The project includes a feasibility study and the preparation of prequalification/tender documents for the following installations:
- The construction of 714 km of 225 kV line
- The extension or new construction of six 225 kV substations in Guinea (N'Zérékoré, Fomi, Beyla, Kérouané, Kankan, Siguiri)
- Additionally, the construction of a new 225 kV substation in Sanankoroba, some 25 km west of Bamako (Mali)
intec's services
- Feasibility study
- Technical study of the interconnection, collection and analysis of data, system study/planning of integrating the new 225 kV line into WAPP's interconnected network (over a time span of 20 years of operation), preliminary design (line, substations, communication and SCADA systems), economic and financial analysis
- Preparation of the prequalification/tender documents and the required split of works into different lots
- Training programme/human resource development for the concerned electricity companies, energy ministries and for staff of the General Directorate of WAPP through training on the job and in the Consultant's home office
Client
West African Power Pool (WAPP) / Système d'Echange d'Energie Electrique Ouest Africain (EEEOA)Financing
African Development BankPeriod of implementation
01.2014 - 06.2016Bangladesh - New 132/33 GIS Substations, a New Cable System and a 4-circuit 132 kV transmission line
The project shall contribute to the Sustainable Power Sector Development Program II by securing proper voltage levels, and thereby reducing transmission losses. This transmission system improvement is necessary to achieve a sustainable restructuring of the power sector. The project includes the following measures:
- Lot 1 - Substations: Construction of new 132/33 kV GIS substations at Lalbagh and Madertak, and conversion of 132/33 kV Dhanmodi transformer station into a regular substation, including construction of an additional 132 kV bay (one and a half breaker scheme) at Rampura Substation
- Lot 2 - Cable system: Construction of a new 132 and 33 kV underground cable system
- Lot 3 - Transmission lines: Construction of 4-circuit 132 kV overhead transmission lines including a river crossing
intec's services
- Assistance to PIU in bid evaluations then drafting the Notice of Award Recommendation
- Assistance in contract negotiations
- Control of Contractor's time schedule
- Assist contractor in obtaining permits and Wayleave Rights
- Approval of Contractor's/suppliers' design
- Participation in Factory Acceptance Tests (FATs)
- Approval of final design and as-built design
- Supervision of construction
- Budget control and invoice review
- Monitoring the training programme
- Assistance to PIU in establishing an operations and maintenance concept
- Assistance in commissioning and assistance during Defects Liability Period (DLP) and warranty period