Grid control systems/SCADA - Project examples
-
Kenya - Power Interconnection Project (KTPIP) (Kenyan Part)
Tanzania and Kenya have joined forces to construct a 400 kV interconnection line that runs from a proposed 400 kV substation at Isinya near Nairobi in Kenya up to Arusha in Tanzania (210 km) and further to a planned 400 kV substation in Singida (300 km). Works in Kenya comprise the following:
- Lot K1: Approx. 96 km of 400 kV transmission line between Isinya Substation and the Kenya-Tanzania border.
intec's services
Phase 0: Procurement
- Contract negotiations and preparation of contract documents with the EPC contractors
Phase 1: Pre-Construction
- Review of EPC Contractors' detailed design
- Elaboration of project management manuals
- Function-based definition of applicable standards and project construction guide documents
Phase 2: Construction
- Supervision and quality control of construction works and commissioning
- Monitoring and follow-up of environmental issues and mitigation measures
- Supervision and clarification of project's cultural heritage issues
- Factory test witnessing
- Organisation of joint site meetings
- Reporting
- Support during the 12-months' Defects Liability Period
Training of Employer's Staff
- On-the-job training on design approval, construction supervision and project management
- Overseas' training for Employer's senior engineers on system planning and network analysis, power system protection and automation, SCADA and telecommunication, power grid operation and maintenance, scheduled and preventive maintenance of HV lines and substations, environmental and social impact assessments (ESIA), resettlement action plans (RAP) and implementation of environmental and social management plans (ESMP)
Client
Kenya Electricity Transmission Company Limited (KETRACO)Financing
African Development Bank, Japanese International Cooperation AgencyPeriod of implementation
2017 - 2020 -
Tanzania - Kenya-Tanzania Power Interconnection Project (KTPIP) (Tanzanian Part)
Tanzania and Kenya have joined forces to construct a 400 kV interconnection line that runs from a proposed 400 kV substation at Isinya near Nairobi in Kenya up to Arusha in Tanzania (210 km) and further to a planned 400 kV substation in Singida (300 km). Works in Tanzania are divided into 6 lots as follows:
- Lot T1: 400 kV double circuit OHL between Singida and Babati (approx. 150 km)
- Lot T2: 400 kV double circuit OHL between Babati and Arusha (approx. 150 km)
- Lot T3: 400 kV double circuit OHL between Arusha and the Kenya border (approx. 114 km)
- Lot T4: New 400 kV Arusha substation and extension of the existing 220/33 kV Singida Substation (two additional 220 kV line bays, three breakers and two shunt reactors)
- Lot T5: Rural electrification projects (approx. 80 km of 33 kV lines and low voltage system including customer connections)
- Lot T6: Four new 400 kV substations in the towns of Iringa, Dodoma, Singida and Shinyanga
intec's services
Phase 0: Procurement
- Contract negotiations and preparation of contract documents with the EPC contractors
Phase 1: Pre-Construction
- Review of EPC Contractors' detailed design
- Elaboration of project management manuals
- Function-based definition of applicable standards and project construction guide documents
Phase 2: Construction
- Supervision and quality control of construction works and commissioning
- Monitoring and follow-up of environmental issues and mitigation measures
- Supervision and clarification of project's cultural heritage issues
- Factory test witnessing
- Organisation of joint site meetings
- Reporting
Training of Employer's Staff
- On-the-job training on design approval, construction supervision and project management
- Overseas training for Employer's senior engineers on system planning and network analysis, power system protection and automation, SCADA and telecommunication, power grid operation and maintenance, scheduled and preventive maintenance of HV lines and substations, environmental and social impact assessments (ESIA), resettlement action plans (RAP) and implementation of environmental and social management plans (ESMP)
Client
Tanzania Electric Supply Company Ltd. (TANESCO)Financing
African Development Bank, Japanese International Cooperation AgencyPeriod of implementation
2017 - 2020 -
Guinea - Implementation of the National Dispatching
The general objective of this project is the monitoring and control of costs, of the quality and the time schedule of implementation works. The project includes all site works for the the National Dispatching Centre implementation. Following EDG's long-term master plan, the National Dispatching Centre shall integrate transmission lines at the level of 60 and 110 kV. The project has been interrupted due to the Ebola epidemic and new financing.
intec's services
- Coordination of activities between the Client EDG and the Contractor
- Check and approval of the Contractor's design and drawings during works execution
- Control of equipment manufacture
- Factory acceptance tests for main equipment
- Monthly / quarterly planning of project activities
- Control of works progress and adherence to the time schedule
- Coordination of meetings and drafting of Minutes of Meetings
- Monitoring of cost and implementation schedule
- Information to the Client about the progress of works and about any difficulties that could hamper smooth project implementation
- Elaboration of periodic progress reports
- Recommendation of necessary intervention measures to the Project Implementation Unit
- Validation of testing and commissioning procedures
- Proposals for settlement of accounts, preliminary and final taking over of works
Client
Electricité de Guinée (EDG)Financing
National Development Budget, Abu Dhabi Fund for Development (ADFD)Period of implementation
05.2014 - 12.2019
Kenya - Power Interconnection Project (KTPIP) (Kenyan Part)
Tanzania and Kenya have joined forces to construct a 400 kV interconnection line that runs from a proposed 400 kV substation at Isinya near Nairobi in Kenya up to Arusha in Tanzania (210 km) and further to a planned 400 kV substation in Singida (300 km). Works in Kenya comprise the following:
- Lot K1: Approx. 96 km of 400 kV transmission line between Isinya Substation and the Kenya-Tanzania border.
intec's services
Phase 0: Procurement
- Contract negotiations and preparation of contract documents with the EPC contractors
Phase 1: Pre-Construction
- Review of EPC Contractors' detailed design
- Elaboration of project management manuals
- Function-based definition of applicable standards and project construction guide documents
Phase 2: Construction
- Supervision and quality control of construction works and commissioning
- Monitoring and follow-up of environmental issues and mitigation measures
- Supervision and clarification of project's cultural heritage issues
- Factory test witnessing
- Organisation of joint site meetings
- Reporting
- Support during the 12-months' Defects Liability Period
Training of Employer's Staff
- On-the-job training on design approval, construction supervision and project management
- Overseas' training for Employer's senior engineers on system planning and network analysis, power system protection and automation, SCADA and telecommunication, power grid operation and maintenance, scheduled and preventive maintenance of HV lines and substations, environmental and social impact assessments (ESIA), resettlement action plans (RAP) and implementation of environmental and social management plans (ESMP)
Client
Kenya Electricity Transmission Company Limited (KETRACO)Financing
African Development Bank, Japanese International Cooperation AgencyPeriod of implementation
2017 - 2020Tanzania - Kenya-Tanzania Power Interconnection Project (KTPIP) (Tanzanian Part)
Tanzania and Kenya have joined forces to construct a 400 kV interconnection line that runs from a proposed 400 kV substation at Isinya near Nairobi in Kenya up to Arusha in Tanzania (210 km) and further to a planned 400 kV substation in Singida (300 km). Works in Tanzania are divided into 6 lots as follows:
- Lot T1: 400 kV double circuit OHL between Singida and Babati (approx. 150 km)
- Lot T2: 400 kV double circuit OHL between Babati and Arusha (approx. 150 km)
- Lot T3: 400 kV double circuit OHL between Arusha and the Kenya border (approx. 114 km)
- Lot T4: New 400 kV Arusha substation and extension of the existing 220/33 kV Singida Substation (two additional 220 kV line bays, three breakers and two shunt reactors)
- Lot T5: Rural electrification projects (approx. 80 km of 33 kV lines and low voltage system including customer connections)
- Lot T6: Four new 400 kV substations in the towns of Iringa, Dodoma, Singida and Shinyanga
intec's services
Phase 0: Procurement
- Contract negotiations and preparation of contract documents with the EPC contractors
Phase 1: Pre-Construction
- Review of EPC Contractors' detailed design
- Elaboration of project management manuals
- Function-based definition of applicable standards and project construction guide documents
Phase 2: Construction
- Supervision and quality control of construction works and commissioning
- Monitoring and follow-up of environmental issues and mitigation measures
- Supervision and clarification of project's cultural heritage issues
- Factory test witnessing
- Organisation of joint site meetings
- Reporting
Training of Employer's Staff
- On-the-job training on design approval, construction supervision and project management
- Overseas training for Employer's senior engineers on system planning and network analysis, power system protection and automation, SCADA and telecommunication, power grid operation and maintenance, scheduled and preventive maintenance of HV lines and substations, environmental and social impact assessments (ESIA), resettlement action plans (RAP) and implementation of environmental and social management plans (ESMP)
Client
Tanzania Electric Supply Company Ltd. (TANESCO)Financing
African Development Bank, Japanese International Cooperation AgencyPeriod of implementation
2017 - 2020Guinea - Implementation of the National Dispatching
The general objective of this project is the monitoring and control of costs, of the quality and the time schedule of implementation works. The project includes all site works for the the National Dispatching Centre implementation. Following EDG's long-term master plan, the National Dispatching Centre shall integrate transmission lines at the level of 60 and 110 kV. The project has been interrupted due to the Ebola epidemic and new financing.
intec's services
- Coordination of activities between the Client EDG and the Contractor
- Check and approval of the Contractor's design and drawings during works execution
- Control of equipment manufacture
- Factory acceptance tests for main equipment
- Monthly / quarterly planning of project activities
- Control of works progress and adherence to the time schedule
- Coordination of meetings and drafting of Minutes of Meetings
- Monitoring of cost and implementation schedule
- Information to the Client about the progress of works and about any difficulties that could hamper smooth project implementation
- Elaboration of periodic progress reports
- Recommendation of necessary intervention measures to the Project Implementation Unit
- Validation of testing and commissioning procedures
- Proposals for settlement of accounts, preliminary and final taking over of works
Client
Electricité de Guinée (EDG)Financing
National Development Budget, Abu Dhabi Fund for Development (ADFD)Period of implementation
05.2014 - 12.2019-
Serbia - Čibuk 1 Wind Farm Project
Vetroelecktrane is developing and executing, together with their major shareholders Abu Dhabi Future Energy Company-Masdar and Continental Wind Partners (CWP), a wind farm consisting of 57 Wind Turbine Generators (WTGs) of 110m hub height and 2.8 MW rated power, 86 km 35 kV cables, main transformer station (35 kV/400 kV; 2x 90 MVA), 11 km double circuit 400 kV OHL and corresponding infrastructure. The consultant has been appointed by the client to manage the project as owner's engineer, providing Project Management Consulting Services (PMC) and site supervision services (including design review, procurement, construction supervision, commissioning, start-up and testing) as well as technical advice and support during negotiations with third parties. The scope includes the following work packages:
- Work Package 2a: Engineering Services
- Work Package 2b: Construction Management and Site Supervision
- EDMS: Electronic Document Management Services
intec's services
- Establish project and document management structures
- Provide technical assistance to the client with any local authorities or other stakeholders.
- Review the design and engineering works carried out by the EPC contractor
- Contribute to the risk assessment (RA)
- Constructability review with the EPC contractors and other stakeholders
- EPC and project documentation review
- Performance of project controls (quality, cost and schedule, document, reporting, testing, factory inspection, health & safety, environmental, site inspection)
- Review of the contractor´s plan for site management and site supervision
- Performance of all health and safety activities prescribed by the Serbian law
- Provide assistance with maintaining compliance with EBRD and IFC requirements
- Supervision of all activities in relation to the connection to the utility network and services performed in relation to the Environmental Management Plan
Client
Vetroelecktrane Balcana (VEBG) D.O.OFinancing
Vetroelecktrane Balcana (VEBG) D.O.OPeriod of implementation
15.03.2017 - 30.11.2019 -
Moldova - Construction of 400 kV Vulcanesti - Chisinau Overhead Transmission Line
The project included the construction of the 400 kV transmission line connecting Vulcanesti Substation to Chisinau Substation and upgrading of the Chisinau and Vulcanesti Substations.
- The existing 330/110/35 kV Chisinau S/S was extended by a new 330 kV bay pertaining to 400/330 kV autotransformer and a new 400 kV bay for OHTL Vulcanesti - Chisinau.
- The 400 kV OHTL Vulcanesti - Chisinau with a length of 157 km, was made on single circuit towers, equipped with three bundle conductors and two earthwires, from which one is of OPGW type to permit optical transmission data.
The existing 400/110/35 kV Vulcanești Substation was extended by a new 400 kV bay for OHTL Vulcanești - Chisinau. In alternative, the OHTL will start from the new BtB Vulcanesti Station.
intec's services
- Review of the existing feasibility and other technical studies: review of proposed technical solutions and concept, identification of alternative line routes or tower locations, if required; preparation of a report to describe the proposed technical solutions and recommendations
- Preparation of preliminary design documents: detailed line routing and profiles, structural design of towers, fabrication and foundation drawings, clearance diagrams; single line diagrams and substation layouts; price schedules and technical data sheets
- Preparation of the bidding documents (World Bank procurement procedures) separately for the substations and the overhead line
Client
Moldova Energy Projects Implementation Unit (MEPIU)Financing
World Bank (WB)Period of implementation
03.2019 - 11.2019 -
Haiti - Construction of a Modern Dispatching
This project constitutes Component 3 of the new investment programme for the energy sector in Haiti (PRELEN), which is supported by the major donors active in the sector. It aims at assisting EDH in the technical field; more specifically in the construction of a modern dispatching.
The existing dispatching was built in 1981 and manages the 115 and 69 kV levels on the generation and transmission side and the 12.47 kV level on the distribution side. The monitoring and dispatching of the network presently is done through permanent surveillance of the system frequency plus by means of radio communication with the substations operators and the power plants.
intec's services
- Implementation studies and detailed engineering; engineering reports
- Preparation of the tender dossiers
- Launching of the tender and assistance during the tender period
- Bid evaluation, preparation of contract documents and contract enforcement
- Organisation and coordination of construction works
- Monitoring and supervision of works, quality control, receipt of material in the factory and on site
- Certification of contractors' invoices
- Preliminary and final acceptance
- Reporting.
Client
Electricité d'Haïti (EDH)Financing
International Development Agency (IDA)Period of implementation
24.10.2017 - 23.10.2019
Serbia - Čibuk 1 Wind Farm Project
Vetroelecktrane is developing and executing, together with their major shareholders Abu Dhabi Future Energy Company-Masdar and Continental Wind Partners (CWP), a wind farm consisting of 57 Wind Turbine Generators (WTGs) of 110m hub height and 2.8 MW rated power, 86 km 35 kV cables, main transformer station (35 kV/400 kV; 2x 90 MVA), 11 km double circuit 400 kV OHL and corresponding infrastructure. The consultant has been appointed by the client to manage the project as owner's engineer, providing Project Management Consulting Services (PMC) and site supervision services (including design review, procurement, construction supervision, commissioning, start-up and testing) as well as technical advice and support during negotiations with third parties. The scope includes the following work packages:
- Work Package 2a: Engineering Services
- Work Package 2b: Construction Management and Site Supervision
- EDMS: Electronic Document Management Services
intec's services
- Establish project and document management structures
- Provide technical assistance to the client with any local authorities or other stakeholders.
- Review the design and engineering works carried out by the EPC contractor
- Contribute to the risk assessment (RA)
- Constructability review with the EPC contractors and other stakeholders
- EPC and project documentation review
- Performance of project controls (quality, cost and schedule, document, reporting, testing, factory inspection, health & safety, environmental, site inspection)
- Review of the contractor´s plan for site management and site supervision
- Performance of all health and safety activities prescribed by the Serbian law
- Provide assistance with maintaining compliance with EBRD and IFC requirements
- Supervision of all activities in relation to the connection to the utility network and services performed in relation to the Environmental Management Plan
Client
Vetroelecktrane Balcana (VEBG) D.O.OFinancing
Vetroelecktrane Balcana (VEBG) D.O.OPeriod of implementation
15.03.2017 - 30.11.2019Moldova - Construction of 400 kV Vulcanesti - Chisinau Overhead Transmission Line
The project included the construction of the 400 kV transmission line connecting Vulcanesti Substation to Chisinau Substation and upgrading of the Chisinau and Vulcanesti Substations.
- The existing 330/110/35 kV Chisinau S/S was extended by a new 330 kV bay pertaining to 400/330 kV autotransformer and a new 400 kV bay for OHTL Vulcanesti - Chisinau.
- The 400 kV OHTL Vulcanesti - Chisinau with a length of 157 km, was made on single circuit towers, equipped with three bundle conductors and two earthwires, from which one is of OPGW type to permit optical transmission data.
The existing 400/110/35 kV Vulcanești Substation was extended by a new 400 kV bay for OHTL Vulcanești - Chisinau. In alternative, the OHTL will start from the new BtB Vulcanesti Station.
intec's services
- Review of the existing feasibility and other technical studies: review of proposed technical solutions and concept, identification of alternative line routes or tower locations, if required; preparation of a report to describe the proposed technical solutions and recommendations
- Preparation of preliminary design documents: detailed line routing and profiles, structural design of towers, fabrication and foundation drawings, clearance diagrams; single line diagrams and substation layouts; price schedules and technical data sheets
- Preparation of the bidding documents (World Bank procurement procedures) separately for the substations and the overhead line
Client
Moldova Energy Projects Implementation Unit (MEPIU)Financing
World Bank (WB)Period of implementation
03.2019 - 11.2019Haiti - Construction of a Modern Dispatching
This project constitutes Component 3 of the new investment programme for the energy sector in Haiti (PRELEN), which is supported by the major donors active in the sector. It aims at assisting EDH in the technical field; more specifically in the construction of a modern dispatching.
The existing dispatching was built in 1981 and manages the 115 and 69 kV levels on the generation and transmission side and the 12.47 kV level on the distribution side. The monitoring and dispatching of the network presently is done through permanent surveillance of the system frequency plus by means of radio communication with the substations operators and the power plants.
intec's services
- Implementation studies and detailed engineering; engineering reports
- Preparation of the tender dossiers
- Launching of the tender and assistance during the tender period
- Bid evaluation, preparation of contract documents and contract enforcement
- Organisation and coordination of construction works
- Monitoring and supervision of works, quality control, receipt of material in the factory and on site
- Certification of contractors' invoices
- Preliminary and final acceptance
- Reporting.
Client
Electricité d'Haïti (EDH)Financing
International Development Agency (IDA)Period of implementation
24.10.2017 - 23.10.2019-
Burkina Faso, Mali - Feasibility studies of solar
The WAPP and the Governments of Mali and Burkina Faso are looking for a Consultant to carry out two technical and financial feasibility studies based on the “Plug & Play” solar park concept in Burkina Faso and Mali. These studies will also aim at defining the optimal strategy for the phasing of the construction of the solar parks with the consideration of storage batteries and their connection to the transmission network. Moreover, these studies will diagnose and evaluate the investments for the reinforcement and modernization of the National Dispatch Centre in view of the integration of solar production.
intec's services
Data collection and review
Determination of the site(s)
- Preliminary study of integration of selected connection substations into the network
- Identification of potential land parcels
- Selection of final sites
- Measurement campaign of solar radiation
Preliminary technical design
Transient stability study of the network for the selected technology
- Integration study
- Connection design
- Control-command and SCADA
Study of production, economic viability and institutional arrangements
Economic and financial studies
Risk studies
Diagnosis and evaluation of investments for the reinforcement and the modernization of the National Dispatch Centre
Training
Reports
Client
West African Power Pool (WAPP)Financing
International Development AssociationPeriod of implementation
01.2019 – 08.2019 -
UAE - 11 kV Power Distribution Network Design (Tawazun Industrial Park - TIP)
Tawazun Industrial Parkis in process for developing 11KV Substation and Cabling works in TIP which involves:
- Supply and Installation of 1500 KVA Package Substation including LV Panels and 11 KV Cablings - 4 to 7 nos based on Load Study.
- Supply and Installation of 3000KVA Substation Including LV Panels and 11KV Cablings - 1 nos
intec's services
Consultancy Services for 11 kV Power Distribution Network Design - 11/0.415 kV Distribution Substations and its associated 11 kV cabling works, 11 kV power supply loop cabling work between Primary Substation and IGT building at Tawazun Industrial Park (TIP), Abu Dhabi
Stage 1 covering:
- Load demand study
- Protection study (Upstream & Downstream)
- LDN development and submission to TIP
- Tender designs
Stage 2 covering:
- Development of tender documents
- Tendering support and Contractor’s Contract documentation covering pre- and post-bid clarifications and Technical & Commercial tender evaluation
Stage 3: Site Supervision
Client
Tawazun Industrial Park (TIP)Financing
Tawazun Industrial Park (TIP)Period of implementation
01.03.2018 - 30.05.2019 -
Cambodia - Extension of the Medium Distribution Grid
The objective of the project is to upgrade and expand distribution and transmission infrastructure for increased access to energy, improved electricity services for the rural population and to contribute to primary energy savings.
The tentative scope of the project is the following:- Component 1: Extension of the medium distribution grid (either 22 kV or/and 35 kV, incl. station transformers) in the rural areas
- Component 2: Construction of two new 115/22 kV grid AIS and GIS substations for strengthening the power evacuation to the 22 kV grid
intec, in its role as the Consultant, shall undertake investigations to assess the technical and economic justification of the planned transmission system expansion.
intec's services
- Brief review of the context of the power sector
- Assessment of the power sub-sector transmission & distribution in the project area, incl. a network analysis
- Survey of AIS and GIS substation areas and review of conceptual AIS and GIS substa-tion design, and provision of an analysis of a potential new AIS and GIS substation
- Review of a future AIS and GIS Substation in the centre of Siem Reap
- Review of proposed enhancement of the MV transmission system
- Identification of additional investment needs
- Conceptual design of the proposed measures
- Review of operation and maintenance concept and identifying training needs
- Cost estimates and investment budget
- Impact assessment and indicators (climate mitigation, access to electricity, local economic development)
- Economic and financial analysis
- Draft implementation concept, procurement plan and project timetable
- Risk assessment
Client
Electricité du Cambodge represented by KfWFinancing
KfW Development BankPeriod of implementation
08.2018 - 02.2019
Burkina Faso, Mali - Feasibility studies of solar
The WAPP and the Governments of Mali and Burkina Faso are looking for a Consultant to carry out two technical and financial feasibility studies based on the “Plug & Play” solar park concept in Burkina Faso and Mali. These studies will also aim at defining the optimal strategy for the phasing of the construction of the solar parks with the consideration of storage batteries and their connection to the transmission network. Moreover, these studies will diagnose and evaluate the investments for the reinforcement and modernization of the National Dispatch Centre in view of the integration of solar production.
intec's services
Data collection and review
Determination of the site(s)
- Preliminary study of integration of selected connection substations into the network
- Identification of potential land parcels
- Selection of final sites
- Measurement campaign of solar radiation
Preliminary technical design
Transient stability study of the network for the selected technology
- Integration study
- Connection design
- Control-command and SCADA
Study of production, economic viability and institutional arrangements
Economic and financial studies
Risk studies
Diagnosis and evaluation of investments for the reinforcement and the modernization of the National Dispatch Centre
Training
Reports
Client
West African Power Pool (WAPP)Financing
International Development AssociationPeriod of implementation
01.2019 – 08.2019UAE - 11 kV Power Distribution Network Design (Tawazun Industrial Park - TIP)
Tawazun Industrial Parkis in process for developing 11KV Substation and Cabling works in TIP which involves:
- Supply and Installation of 1500 KVA Package Substation including LV Panels and 11 KV Cablings - 4 to 7 nos based on Load Study.
- Supply and Installation of 3000KVA Substation Including LV Panels and 11KV Cablings - 1 nos
intec's services
Consultancy Services for 11 kV Power Distribution Network Design - 11/0.415 kV Distribution Substations and its associated 11 kV cabling works, 11 kV power supply loop cabling work between Primary Substation and IGT building at Tawazun Industrial Park (TIP), Abu Dhabi
Stage 1 covering:
- Load demand study
- Protection study (Upstream & Downstream)
- LDN development and submission to TIP
- Tender designs
Stage 2 covering:
- Development of tender documents
- Tendering support and Contractor’s Contract documentation covering pre- and post-bid clarifications and Technical & Commercial tender evaluation
Stage 3: Site Supervision
Client
Tawazun Industrial Park (TIP)Financing
Tawazun Industrial Park (TIP)Period of implementation
01.03.2018 - 30.05.2019Cambodia - Extension of the Medium Distribution Grid
The objective of the project is to upgrade and expand distribution and transmission infrastructure for increased access to energy, improved electricity services for the rural population and to contribute to primary energy savings.
The tentative scope of the project is the following:
- Component 1: Extension of the medium distribution grid (either 22 kV or/and 35 kV, incl. station transformers) in the rural areas
- Component 2: Construction of two new 115/22 kV grid AIS and GIS substations for strengthening the power evacuation to the 22 kV grid
intec, in its role as the Consultant, shall undertake investigations to assess the technical and economic justification of the planned transmission system expansion.
intec's services
- Brief review of the context of the power sector
- Assessment of the power sub-sector transmission & distribution in the project area, incl. a network analysis
- Survey of AIS and GIS substation areas and review of conceptual AIS and GIS substa-tion design, and provision of an analysis of a potential new AIS and GIS substation
- Review of a future AIS and GIS Substation in the centre of Siem Reap
- Review of proposed enhancement of the MV transmission system
- Identification of additional investment needs
- Conceptual design of the proposed measures
- Review of operation and maintenance concept and identifying training needs
- Cost estimates and investment budget
- Impact assessment and indicators (climate mitigation, access to electricity, local economic development)
- Economic and financial analysis
- Draft implementation concept, procurement plan and project timetable
- Risk assessment