Projects worldwide
intec has executed and is implementing large and complex projects in nearly all regions of the world.
The projects listed on the website represent only a handful of our references.
Our Projects
-
Mauritania - Construction of a 120 (180) MW dual-fuel power plant in Nouakchott
The state-owned utility SOMELEC is currently constructing a new power plant in Nouakchott to answer the steadily increasing power demand in the city and eventually in the national and international grid. This power plant, in its initial phase, had a capacity of 120 MW (8 x 15 MW dual-fuel gen sets, operated either with HFO or gas). In the second phase, the plant is currently extended to 180 MW capacity by adding a further four gen sets.
intec's services
- Choice of site for the power plant
- Review of the existing design report and preparation of tender documents
- Assistance to SOMELEC during tendering, tender evaluation, contract negotiation and contract conclusion
- Follow-up, coordination and control of design studies and manufacturing
- Supervision, monitoring and coordination of site works
- Verification of equipment lists
- Implementation of the training plan for the future operating personnel
- Preparation of tender documents for the power plant access road, follow-up, coordination and control of construction.
Client
SOMELEC - Mauritanian Electricity CompanyFinancing
Arab Fund for Economic and Social DevelopmentPeriod of implementation
08.2011 - 06.2017 -
Nigeria - "Transmission Lines and Associated Substation Agreement" for the 80 MW AC Nova Scotia Solar PV Project
Nova Scotia Power Development Limited (NSPDL) is developing a ground-mounted 80 MW (AC) solar PV plant. The proposed site is located some 5 km from the town of Dutse in Jigawa State. The proposed plant will be connected to the national transmission grid by means of a 132 kV double-circuit overhead line between the step-up transformer at the PV site to the 33/132 kV Dutse Substation. It will be owned and operated by the Transmission Company of Nigeria (TCN). The interconnection facility will be financed and constructed by NSPDL. Ownership will however be transferred to TCN upon commissioning.
The project consists of advisory services to NSPDL for the completion and negotiation of a ‘Transmission Lines and Associated Substation Agreement’ with TCN.
intec's services
- Technical review and provision of comments on the body of the agreement
- Completion of technical schedules, e.g.
- Development of a design basis document
- Development of the acceptance tests and criteria
- Assistance in scheduling the required meetings between NSPDL and TCN
- Advice to NSPDL in negotiating and executing the agreement with TCN
Client
Nova Scotia Power Development Limited (NSPDL)Financing
Nova Scotia Power Development Limited (NSPDL)Period of implementation
04.2017 - 06.2017 -
Rwanda, Burundi - Regional Interconnection Project (220 kV Transmission Line Kigoma - Butare - Ngozi - Gitega and 220/110 kV Substations)
The project was part of the NELSAP Regional Transmission Program that aimed at interconnecting five of the Nile Equatorial Lakes Countries, i.e. Burundi, DR Congo, Kenya, Rwanda and Uganda.
The project interconnected the electricity networks of Burundi and Rwanda through the construction of a new 220 kV single-circuit transmission line with a total length of 143 km. The line will initially be operated on the 110 kV level and might later be upgraded to 220 kV.
The project also included the construction of two new 220/110 kV substations, the extension of two existing 110 kV substations and the construction of 11.2 km of 30 kV line for rural electrification of Gisagara (Rwanda).
intec's services
- Review of existing feasibility studies
- Update of the Environmental and Social Management Plan (ESMP)
- Detailed design
- Preparation of complete tender documents for EPC Contractors (2 lots)
- Technical assistance during the procurement process, i.e. tendering, bid evaluation and contract award
- Preparation of a detailed Resettlement Action Plan (RAP) and monitoring of its implementation
- Design approval and supervision of implementation works
- Witnessing of factory acceptance tests, supervision of testing and commissioning
- Certification of Contractor's invoices and payments
- Monitoring and supervision of the implementation of the ESMP
- Safeguarding of project's compliance with KfW's and the World Bank's sustainability guidelines
- Technology transfer and training of employers' and project executing agency's staff
- Representation in the respective project steering and technical committees
Client
REGIDESO (Burundi), Energy Development Corporation Ltd. (Rwanda)Financing
KfW EntwicklungsbankPeriod of implementation
03.2015 - 06.2017
Mauritania - Construction of a 120 (180) MW dual-fuel power plant in Nouakchott
The state-owned utility SOMELEC is currently constructing a new power plant in Nouakchott to answer the steadily increasing power demand in the city and eventually in the national and international grid. This power plant, in its initial phase, had a capacity of 120 MW (8 x 15 MW dual-fuel gen sets, operated either with HFO or gas). In the second phase, the plant is currently extended to 180 MW capacity by adding a further four gen sets.
intec's services
- Choice of site for the power plant
- Review of the existing design report and preparation of tender documents
- Assistance to SOMELEC during tendering, tender evaluation, contract negotiation and contract conclusion
- Follow-up, coordination and control of design studies and manufacturing
- Supervision, monitoring and coordination of site works
- Verification of equipment lists
- Implementation of the training plan for the future operating personnel
- Preparation of tender documents for the power plant access road, follow-up, coordination and control of construction.
Client
SOMELEC - Mauritanian Electricity CompanyFinancing
Arab Fund for Economic and Social DevelopmentPeriod of implementation
08.2011 - 06.2017Nigeria - "Transmission Lines and Associated Substation Agreement" for the 80 MW AC Nova Scotia Solar PV Project
Nova Scotia Power Development Limited (NSPDL) is developing a ground-mounted 80 MW (AC) solar PV plant. The proposed site is located some 5 km from the town of Dutse in Jigawa State. The proposed plant will be connected to the national transmission grid by means of a 132 kV double-circuit overhead line between the step-up transformer at the PV site to the 33/132 kV Dutse Substation. It will be owned and operated by the Transmission Company of Nigeria (TCN). The interconnection facility will be financed and constructed by NSPDL. Ownership will however be transferred to TCN upon commissioning.
The project consists of advisory services to NSPDL for the completion and negotiation of a ‘Transmission Lines and Associated Substation Agreement’ with TCN.
intec's services
- Technical review and provision of comments on the body of the agreement
- Completion of technical schedules, e.g.
- Development of a design basis document
- Development of the acceptance tests and criteria
- Assistance in scheduling the required meetings between NSPDL and TCN
- Advice to NSPDL in negotiating and executing the agreement with TCN
Client
Nova Scotia Power Development Limited (NSPDL)Financing
Nova Scotia Power Development Limited (NSPDL)Period of implementation
04.2017 - 06.2017Rwanda, Burundi - Regional Interconnection Project (220 kV Transmission Line Kigoma - Butare - Ngozi - Gitega and 220/110 kV Substations)
The project was part of the NELSAP Regional Transmission Program that aimed at interconnecting five of the Nile Equatorial Lakes Countries, i.e. Burundi, DR Congo, Kenya, Rwanda and Uganda.
The project interconnected the electricity networks of Burundi and Rwanda through the construction of a new 220 kV single-circuit transmission line with a total length of 143 km. The line will initially be operated on the 110 kV level and might later be upgraded to 220 kV.
The project also included the construction of two new 220/110 kV substations, the extension of two existing 110 kV substations and the construction of 11.2 km of 30 kV line for rural electrification of Gisagara (Rwanda).
intec's services
- Review of existing feasibility studies
- Update of the Environmental and Social Management Plan (ESMP)
- Detailed design
- Preparation of complete tender documents for EPC Contractors (2 lots)
- Technical assistance during the procurement process, i.e. tendering, bid evaluation and contract award
- Preparation of a detailed Resettlement Action Plan (RAP) and monitoring of its implementation
- Design approval and supervision of implementation works
- Witnessing of factory acceptance tests, supervision of testing and commissioning
- Certification of Contractor's invoices and payments
- Monitoring and supervision of the implementation of the ESMP
- Safeguarding of project's compliance with KfW's and the World Bank's sustainability guidelines
- Technology transfer and training of employers' and project executing agency's staff
- Representation in the respective project steering and technical committees
Client
REGIDESO (Burundi), Energy Development Corporation Ltd. (Rwanda)Financing
KfW EntwicklungsbankPeriod of implementation
03.2015 - 06.2017-
Mauritania - Construction of Solar Hybrid Systems with 16.6 MW Solar Capacity
MASDAR is developing various small and large-scale solar and wind projects in the Pacific and other regions of the world and sourced a pool of experts to support the engineering and project management team. These support tasks are contracted separately in the form of so-called Work Orders (WO). They include feasibility studies, conceptual designs, preparation of tender documents, evaluation of bids and on- and off-site project management.
Under the current work order, all together eight hybrid systems in the range up to several MW per site and with at total solar capacity of 16.6 MW (range from 1 to 3.4 MW) will be implemented under an EPC approach. Each power plant consists of solar PV, controller, and diesel generator.
intec's services
- Tasks of the "owner's representative", including coordination between the Mauritanian Electricity Company and the EPC contractor
- Design review
- Review of project execution plan
- Inspection of project construction works including QA and QC;
- Review of payment milestones
- Inspection of works' progress
- QHSE audit on all sites and submission of related report
Client
Abu Dhabi Future Energy Company PJSC - MASDARFinancing
MASDARPeriod of implementation
01.2016 - 06.2017 -
Congo (RD) - Revision of the Studies on the 220 kV Line Kamanyola - Buhandahanda
The 220 kV Kamanyola - Buhandahanda line shall evacuate the electricity generated by the Ruzizi III Hydropower Plant, which is part of the 220 kV interconnected network of the CEPGL (Communauté Economique des Pays des Grands Lacs - Economic Community of the Great Lake Countries). Studies for this line were finalised in September 2011 and shall be revised under the present project. The aim is to take into consideration the new locations of the Kamanyola and Buhandahanda Substations, and the new line concept.
intec's services
- Review of the project's technical feasibility; in particular through revision of the line's general concept (review of the line route and harmonisation of the design/double-circuit line with possibly only one single circuit operated in the first phase), study of the grid stability with the new line, set-up of a simulation model of the interconnected network, power distribution and load flow studies, review of the line protection system)
- Review of the project's economic and financial feasibility (cost estimates, economic and financial viability, proposals for project financing and implementation)
- Preparation of the detailed design for the revised line concept, elaboration of the longitudinal profile on the basis of satellite data, and tower spotting
- Preparation of an Environmental and Social Impact Assessment (ESIA) and an Environmental Management Plan (EMP) to conform with international standards, and elaboration of a Resettlement Action Plan (RAP)
- Elaboration of the tender dossier
- Organisation of a validation seminar with EGL, SNEL (National Power Company of Congo), the Steering Committee and KfW
- Participation in the project appraisal mission
Client
Energie des Grands Lacs - EGLFinancing
KfW EntwicklungsbankPeriod of implementation
07.2015 - 03.2017 -
Lithuania - Transfer-Back Inspection of Heating Installations in Vilnius
The project is part of a transfer-back of heating installations in the framework of a leasing procedure. It aims at establishing the technical conditions of the leased facilities that were used for district heating in Vilnius city.
These facilities include inter alia:- Steam and water heating boilers, including fuel system, pressure vessels, pipelines, turbines, preparation and supply system for chemically treated and feed water, condensate collection systems, pressurised air systems, flue gas treatment and ash removal systems, consumer heat meters, etc.
- Electricity generators and transformers, including distribution equipment, electric motors, etc.
- Infrastructure equipment: lifting equipment, railway infrastructure, heat supply networks, etc.
- Real estate (building and engineering structures)
- Information and telecommunication systems and data (software, hardware, etc.)
intec's services
Establishment of the technical condition by means of:
- Visual inspection of facilities
- Inspection of facilities in operation and tests of system functioning
- Identification of maintenance and repair works carried out during the last 5 years
Drawing-up of a report on that condition.
Client
UAB "Vilniaus energija", VEOLIA Environnement, AB "Vilniaus silumos tinklai", Vilnius City MunicipalityFinancing
UAB "Vilniaus energija", VEOLIA Environnement, AB "Vilniaus silumos tinklai", Vilnius City MunicipalityPeriod of implementation
01.2017 - 03.2017
Mauritania - Construction of Solar Hybrid Systems with 16.6 MW Solar Capacity
MASDAR is developing various small and large-scale solar and wind projects in the Pacific and other regions of the world and sourced a pool of experts to support the engineering and project management team. These support tasks are contracted separately in the form of so-called Work Orders (WO). They include feasibility studies, conceptual designs, preparation of tender documents, evaluation of bids and on- and off-site project management.
Under the current work order, all together eight hybrid systems in the range up to several MW per site and with at total solar capacity of 16.6 MW (range from 1 to 3.4 MW) will be implemented under an EPC approach. Each power plant consists of solar PV, controller, and diesel generator.
intec's services
- Tasks of the "owner's representative", including coordination between the Mauritanian Electricity Company and the EPC contractor
- Design review
- Review of project execution plan
- Inspection of project construction works including QA and QC;
- Review of payment milestones
- Inspection of works' progress
- QHSE audit on all sites and submission of related report
Client
Abu Dhabi Future Energy Company PJSC - MASDARFinancing
MASDARPeriod of implementation
01.2016 - 06.2017Congo (RD) - Revision of the Studies on the 220 kV Line Kamanyola - Buhandahanda
The 220 kV Kamanyola - Buhandahanda line shall evacuate the electricity generated by the Ruzizi III Hydropower Plant, which is part of the 220 kV interconnected network of the CEPGL (Communauté Economique des Pays des Grands Lacs - Economic Community of the Great Lake Countries). Studies for this line were finalised in September 2011 and shall be revised under the present project. The aim is to take into consideration the new locations of the Kamanyola and Buhandahanda Substations, and the new line concept.
intec's services
- Review of the project's technical feasibility; in particular through revision of the line's general concept (review of the line route and harmonisation of the design/double-circuit line with possibly only one single circuit operated in the first phase), study of the grid stability with the new line, set-up of a simulation model of the interconnected network, power distribution and load flow studies, review of the line protection system)
- Review of the project's economic and financial feasibility (cost estimates, economic and financial viability, proposals for project financing and implementation)
- Preparation of the detailed design for the revised line concept, elaboration of the longitudinal profile on the basis of satellite data, and tower spotting
- Preparation of an Environmental and Social Impact Assessment (ESIA) and an Environmental Management Plan (EMP) to conform with international standards, and elaboration of a Resettlement Action Plan (RAP)
- Elaboration of the tender dossier
- Organisation of a validation seminar with EGL, SNEL (National Power Company of Congo), the Steering Committee and KfW
- Participation in the project appraisal mission
Client
Energie des Grands Lacs - EGLFinancing
KfW EntwicklungsbankPeriod of implementation
07.2015 - 03.2017Lithuania - Transfer-Back Inspection of Heating Installations in Vilnius
The project is part of a transfer-back of heating installations in the framework of a leasing procedure. It aims at establishing the technical conditions of the leased facilities that were used for district heating in Vilnius city.
These facilities include inter alia:
- Steam and water heating boilers, including fuel system, pressure vessels, pipelines, turbines, preparation and supply system for chemically treated and feed water, condensate collection systems, pressurised air systems, flue gas treatment and ash removal systems, consumer heat meters, etc.
- Electricity generators and transformers, including distribution equipment, electric motors, etc.
- Infrastructure equipment: lifting equipment, railway infrastructure, heat supply networks, etc.
- Real estate (building and engineering structures)
- Information and telecommunication systems and data (software, hardware, etc.)
intec's services
Establishment of the technical condition by means of:
- Visual inspection of facilities
- Inspection of facilities in operation and tests of system functioning
- Identification of maintenance and repair works carried out during the last 5 years
Drawing-up of a report on that condition.