Power distribution systems - Project examples
-
Mauritania - Development of the Eastern Zone Electricity Systems
The project included studies and works supervision services for the following technical measures:
- Construction of hybrid thermal power plants (PV) with related energy storage:
Néma Power Plant: 4 MW diesel, 2 MW solar PV, 500 kW energy storage,
Adel Bagrou Power Plant: 2 MW diesel, 1 MW solar PV, 250 kW energy storage.- Construction of 15, 33, 90 and 225 kV lines:
Centre line Néma - Achemim - Derouich Water Catchment Area (126 km line and MV/LV substations)
Centre line Néma - Amourj - Adel Bagrou - Boghle Water Catchment Area (3 lines with a total length of 255 km, and HV/LV substations)
Centre line Néma - Timbédra (170 km line and HV/LV substations)
Centre line Aioun - Doueirare (35 km line and HV/LV substations)- Reinforcement and development of new electricity distribution networks (0.4 - 33 kV).
intec's services
Phase 1: Studies and Assistance to the Client
- Execution of detailed engineering
- Execution of detailed design
- Establishment of tender documents
- Assistance to SOMELEC during the procurement phase, from tender launch to conclusion of the contracts with the Contractors
- Environmental and social impact assessment
Phase 2: Monitoring and Supervision of Works
- Monitoring of the implementation studies
Monitoring of equipment manufacturing
Participation in testing and factory acceptance tests (FATs)
Supervision and control of works
Monitoring the training of SOMELEC's staff
Client
SOMELECFinancing
Mauritanian GovernmentPeriod of implementation
03.2013 - 12.2018 -
Tanzania - Zanzibar Renewable Energies and Energy Efficiency Programme
The EU has formulated a comprehensive programme to support the RE and EE Initiative in Zanzibar. This includes the supply and installation of wind and solar measurement equipment (separately contracted) and the recruitment of consultancy services for the implementation of the programme in 2 lots: the present study work (Lot 1) and technical assistance for the implementation of RE and EE projects to be separately contracted as Lot 2.
intec's services
- Collection and analysis of wind and solar resource data for a period of 12 months resulting in a wind map for the archipelago, in the confirmation of 5 wind sites and of 3 solar farm sites for feasibility analyses
- Grid impact study: load flow, static and dynamic analysis, maximum penetration estimation, capacity factor calculation, estimation of needed rotational reserve and report preparation.
- Logistics study for wind parks and solar farms (harbour/landing facilities, transport and construction equipment, access roads, etc.; development of a logistics plan)
- Wind flow modelling for selected sites and solar PV potential, inter alia development of a digital terrain model (DTM) for the pre-selected sites
- Output prediction for wind parks and solar PV farms incl. selection of wind turbines and PV panels to consider, loss and risk analyses
- Feasibility studies for wind parks, solar farms and solar home systems (SHS), incl. preliminary project designs and cost estimates, grid integration studies (33 kV), SCADA, civil engineering, financial and economic analyses, preliminary standardized design of SHS, and procurement and construction schedule
- Evaluation of regulatory requirements (permits and licenses, land use, laws on construction and operation of wind parks and solar farms)
- Environmental and social impact assessments (EIA and SIA), including development of an environmental monitoring and management plan (EMMP)
Client
The Alternate National Authorizing Officer (NAO), Ministry of FinanceFinancing
European CommissionPeriod of implementation
1.8.2015 - 01.09.2018 -
Iraq - Technical Support for the German "Credit Facility to Assist the Return of IDPs" in Iraq
Germany’s government, via the KfW, provides a credit facility (United Financial Loan or UFL) for stabilization/recovery of liberated territories, and to assist the return of Internally Displaced Persons (IDPs). Part of the project is the assistance to the Ministry of Electricity (MoE) in the preparation of an investment programme (‘investment measure’) and a related technical support component (‘accompanying measure’), to assess and plan measures for the rehabilitation of the transmission/distribution networks for re-establishing power feeders to the end users. This results in an ‘Investment Plan for the Power Sector in Northern Iraq’, consisting of Phase I for immediate implementation, then Phase II for complementary required investments.
Measures identified for Phase I include the rehabilitation of one 132/33 kV, 3 x 63 MVA GIS substations and three 132/33/11 kV AIS substations, supply of three 132/33/11 kV, 3 x 63 MVA power transformers, supply of 132 kV transmission line towers and accessories for rehabilitation of six transmission lines, supply of eight 33/11 kV, 31.5 MVA mobile substations, five 33/11 kV, 31.5 MVA power transformers and supply of distribution transformers 11/0.4 kV, different power ratings, as well as distribution kiosks and accessories.
Measures identified for Phase II include the rehabilitation of a 400/132/11 kV, 4 x 250 MV GIS substation, the construction of two new 132/33 kV, 3 x 63 MVA GIS substations, the construction of two new 33/11 kV, 3 x 31.5 MVA distribution substations and the construction of 154 km new double circuit transmission line
intec's services
- Analysis of relevant data collected from MoE, KfW and other institutions, i. a. a list of priority projects
- Mission to Baghdad for interviews and collection of additional information
- Evaluation of the current energy supply and definition of the baseline scenario in the target regions
- Analysis of different investment measures (distribution/transmission), based on predefined criteria and proposing suitable investments
- Selection of appropriate investment schedules and procurement packages
- Preparation of an implementation plan and presenting results in a workshop with key stakeholders
- Preparation of tender documents
- Support to the Ministry of Electricity during tendering, tender evaluation and finalisation of contracts.)
- Preparation of ESMP document
Client
KfW EntwicklungsbankFinancing
KfW EntwicklungsbankPeriod of implementation
5.7.2017 - 31.8.2018
Mauritania - Development of the Eastern Zone Electricity Systems
The project included studies and works supervision services for the following technical measures:
- Construction of hybrid thermal power plants (PV) with related energy storage:
Néma Power Plant: 4 MW diesel, 2 MW solar PV, 500 kW energy storage,
Adel Bagrou Power Plant: 2 MW diesel, 1 MW solar PV, 250 kW energy storage.
- Construction of 15, 33, 90 and 225 kV lines:
Centre line Néma - Achemim - Derouich Water Catchment Area (126 km line and MV/LV substations)
Centre line Néma - Amourj - Adel Bagrou - Boghle Water Catchment Area (3 lines with a total length of 255 km, and HV/LV substations)
Centre line Néma - Timbédra (170 km line and HV/LV substations)
Centre line Aioun - Doueirare (35 km line and HV/LV substations)
- Reinforcement and development of new electricity distribution networks (0.4 - 33 kV).
intec's services
Phase 1: Studies and Assistance to the Client
- Execution of detailed engineering
- Execution of detailed design
- Establishment of tender documents
- Assistance to SOMELEC during the procurement phase, from tender launch to conclusion of the contracts with the Contractors
- Environmental and social impact assessment
Phase 2: Monitoring and Supervision of Works
- Monitoring of the implementation studies
Monitoring of equipment manufacturing
Participation in testing and factory acceptance tests (FATs)
Supervision and control of works
Monitoring the training of SOMELEC's staff
Client
SOMELECFinancing
Mauritanian GovernmentPeriod of implementation
03.2013 - 12.2018Tanzania - Zanzibar Renewable Energies and Energy Efficiency Programme
The EU has formulated a comprehensive programme to support the RE and EE Initiative in Zanzibar. This includes the supply and installation of wind and solar measurement equipment (separately contracted) and the recruitment of consultancy services for the implementation of the programme in 2 lots: the present study work (Lot 1) and technical assistance for the implementation of RE and EE projects to be separately contracted as Lot 2.
intec's services
- Collection and analysis of wind and solar resource data for a period of 12 months resulting in a wind map for the archipelago, in the confirmation of 5 wind sites and of 3 solar farm sites for feasibility analyses
- Grid impact study: load flow, static and dynamic analysis, maximum penetration estimation, capacity factor calculation, estimation of needed rotational reserve and report preparation.
- Logistics study for wind parks and solar farms (harbour/landing facilities, transport and construction equipment, access roads, etc.; development of a logistics plan)
- Wind flow modelling for selected sites and solar PV potential, inter alia development of a digital terrain model (DTM) for the pre-selected sites
- Output prediction for wind parks and solar PV farms incl. selection of wind turbines and PV panels to consider, loss and risk analyses
- Feasibility studies for wind parks, solar farms and solar home systems (SHS), incl. preliminary project designs and cost estimates, grid integration studies (33 kV), SCADA, civil engineering, financial and economic analyses, preliminary standardized design of SHS, and procurement and construction schedule
- Evaluation of regulatory requirements (permits and licenses, land use, laws on construction and operation of wind parks and solar farms)
- Environmental and social impact assessments (EIA and SIA), including development of an environmental monitoring and management plan (EMMP)
Client
The Alternate National Authorizing Officer (NAO), Ministry of FinanceFinancing
European CommissionPeriod of implementation
1.8.2015 - 01.09.2018Iraq - Technical Support for the German "Credit Facility to Assist the Return of IDPs" in Iraq
Germany’s government, via the KfW, provides a credit facility (United Financial Loan or UFL) for stabilization/recovery of liberated territories, and to assist the return of Internally Displaced Persons (IDPs). Part of the project is the assistance to the Ministry of Electricity (MoE) in the preparation of an investment programme (‘investment measure’) and a related technical support component (‘accompanying measure’), to assess and plan measures for the rehabilitation of the transmission/distribution networks for re-establishing power feeders to the end users. This results in an ‘Investment Plan for the Power Sector in Northern Iraq’, consisting of Phase I for immediate implementation, then Phase II for complementary required investments.
Measures identified for Phase I include the rehabilitation of one 132/33 kV, 3 x 63 MVA GIS substations and three 132/33/11 kV AIS substations, supply of three 132/33/11 kV, 3 x 63 MVA power transformers, supply of 132 kV transmission line towers and accessories for rehabilitation of six transmission lines, supply of eight 33/11 kV, 31.5 MVA mobile substations, five 33/11 kV, 31.5 MVA power transformers and supply of distribution transformers 11/0.4 kV, different power ratings, as well as distribution kiosks and accessories.
Measures identified for Phase II include the rehabilitation of a 400/132/11 kV, 4 x 250 MV GIS substation, the construction of two new 132/33 kV, 3 x 63 MVA GIS substations, the construction of two new 33/11 kV, 3 x 31.5 MVA distribution substations and the construction of 154 km new double circuit transmission line
intec's services
- Analysis of relevant data collected from MoE, KfW and other institutions, i. a. a list of priority projects
- Mission to Baghdad for interviews and collection of additional information
- Evaluation of the current energy supply and definition of the baseline scenario in the target regions
- Analysis of different investment measures (distribution/transmission), based on predefined criteria and proposing suitable investments
- Selection of appropriate investment schedules and procurement packages
- Preparation of an implementation plan and presenting results in a workshop with key stakeholders
- Preparation of tender documents
- Support to the Ministry of Electricity during tendering, tender evaluation and finalisation of contracts.)
- Preparation of ESMP document
Client
KfW EntwicklungsbankFinancing
KfW EntwicklungsbankPeriod of implementation
5.7.2017 - 31.8.2018-
Niger - PV Hybridization of Diesel-Based Mini-Grids in Niger
The Government of Niger has been striving to increase electricity access and has set an ambitious goal of increasing the access rate to 60% by 2027. The objective of this assignment is to conduct the feasibility study of the hybridization with PV and expansion of access to electricity of several existing diesel-based isolated grids throughout Niger and managed by NIGELEC.
intec's services
- Georeferencing and analysis (GIS) of mini grids managed by NIGELEC
- Analysis of hybridization options and potential for grid expansion and access increase of access to electricity
- Elaboration of pre-feasibility study of the selected isolated grids
- Mid-term workshop to select final set for feasibility studies
- Site visit to each of the selected isolated grids at the feasibility stage, including demand assessment
- Elaboration of feasibility study of the selected isolated grids
- Training with national stakeholders
Client
World BankFinancing
World BankPeriod of implementation
02.11.2016 - 30.06.2018 -
Guinea - Conakry Electrical Networks (PREREC 2)
PREREC 2 aims at contributing to the improvement of the government and financial management of EDG, at assisting the government in the reform of the subsector and at extending the electricity distribution network in the Lambandji, Kobaya, Wanindara and Yattayah quarters of the country's capital. It is a follow-up to the first project, PREREC 1.
The project foresees the construction of the following installations:
- 20 km of mixed MV/LV lines
- 87 km of LV lines
- 49 kiosk MV/LV substations
- 20,000 consumer connections and installation of 20,000 prepaid meters
- 3,500 street lighting units
intec's services
- Technical control of design
- Inspection of equipment and materials in the factory
- Supervision of works on the site
- Commissioning testing
- Final taking-over
- Delivery of all professional and technical services and assistance in line with FIDIC directives
- On-the-job training
Client
Electricité de Guinée (EDG)Financing
African Development Fund (ADF)Period of implementation
2015 - 2018 -
Mauritania - Solar Energy-Based Rural Electrification in the Aftout Elchargui Region
The Mauritanian Government initiated a national strategy to provide universal access to basic services (water, energy, telecommunication) in rural and suburban areas. In this context, the Government received a loan from the Islamic Development Bank and the OPEC Fund for International Development (OFID) for the implementation of strategic investments in electricity infrastructure, one of the components being consultancy services for project supervision. The project includes mainly:
- the procurement and installation of (i) one solar PV plant with an estimated capacity of 2.6 MWc and storage, (ii) a diesel back-up system to complement the electricity production (2 diesel gensets), and the optimisation of the envisaged electricity production as per the prevailing conditions
- the construction of approx. 270 km of HV transmission networks and approx. 60 km of LV distribution networks as well as approx. 6,000 consumer connections
intec's services
Mission 1: Detailed technical studies, including environmental and social impact studies for the equipment which is divided into 3 lots (power plants and their optimisation, HV networks, LV networks): Elaboration of preliminary design and detailed design for the chosen options, including technical specifications and dimensioning, engineering, functional specifications for the equipment, soil investigations, topography, BoQ etc., and elaboration of tender documents.
Mission 2: Support to the Employer during tendering: Site visits with the Bidders, reply to Bidders' queries, bid evaluation and support to the Employer during contract negotiations for the EPC contracts.
Mission 3: Technical control and supervision of works: Management of the implementation works, scheduling and steering of site works, and assistance during acceptance operations.
Client
Agence de Promotion de l'Accès Universel aux Services (APAUS)Financing
Islamic Development Bank (IDB)Period of implementation
2016 - 2018
Niger - PV Hybridization of Diesel-Based Mini-Grids in Niger
The Government of Niger has been striving to increase electricity access and has set an ambitious goal of increasing the access rate to 60% by 2027. The objective of this assignment is to conduct the feasibility study of the hybridization with PV and expansion of access to electricity of several existing diesel-based isolated grids throughout Niger and managed by NIGELEC.
intec's services
- Georeferencing and analysis (GIS) of mini grids managed by NIGELEC
- Analysis of hybridization options and potential for grid expansion and access increase of access to electricity
- Elaboration of pre-feasibility study of the selected isolated grids
- Mid-term workshop to select final set for feasibility studies
- Site visit to each of the selected isolated grids at the feasibility stage, including demand assessment
- Elaboration of feasibility study of the selected isolated grids
- Training with national stakeholders
Client
World BankFinancing
World BankPeriod of implementation
02.11.2016 - 30.06.2018Guinea - Conakry Electrical Networks (PREREC 2)
PREREC 2 aims at contributing to the improvement of the government and financial management of EDG, at assisting the government in the reform of the subsector and at extending the electricity distribution network in the Lambandji, Kobaya, Wanindara and Yattayah quarters of the country's capital. It is a follow-up to the first project, PREREC 1.
The project foresees the construction of the following installations:
- 20 km of mixed MV/LV lines
- 87 km of LV lines
- 49 kiosk MV/LV substations
- 20,000 consumer connections and installation of 20,000 prepaid meters
- 3,500 street lighting units
intec's services
- Technical control of design
- Inspection of equipment and materials in the factory
- Supervision of works on the site
- Commissioning testing
- Final taking-over
- Delivery of all professional and technical services and assistance in line with FIDIC directives
- On-the-job training
Client
Electricité de Guinée (EDG)Financing
African Development Fund (ADF)Period of implementation
2015 - 2018Mauritania - Solar Energy-Based Rural Electrification in the Aftout Elchargui Region
The Mauritanian Government initiated a national strategy to provide universal access to basic services (water, energy, telecommunication) in rural and suburban areas. In this context, the Government received a loan from the Islamic Development Bank and the OPEC Fund for International Development (OFID) for the implementation of strategic investments in electricity infrastructure, one of the components being consultancy services for project supervision. The project includes mainly:
- the procurement and installation of (i) one solar PV plant with an estimated capacity of 2.6 MWc and storage, (ii) a diesel back-up system to complement the electricity production (2 diesel gensets), and the optimisation of the envisaged electricity production as per the prevailing conditions
- the construction of approx. 270 km of HV transmission networks and approx. 60 km of LV distribution networks as well as approx. 6,000 consumer connections
intec's services
Mission 1: Detailed technical studies, including environmental and social impact studies for the equipment which is divided into 3 lots (power plants and their optimisation, HV networks, LV networks): Elaboration of preliminary design and detailed design for the chosen options, including technical specifications and dimensioning, engineering, functional specifications for the equipment, soil investigations, topography, BoQ etc., and elaboration of tender documents.
Mission 2: Support to the Employer during tendering: Site visits with the Bidders, reply to Bidders' queries, bid evaluation and support to the Employer during contract negotiations for the EPC contracts.
Mission 3: Technical control and supervision of works: Management of the implementation works, scheduling and steering of site works, and assistance during acceptance operations.
Client
Agence de Promotion de l'Accès Universel aux Services (APAUS)Financing
Islamic Development Bank (IDB)Period of implementation
2016 - 2018-
ECOWAS Region - Support to RE Flagship Projects
ECOWAS, the Economic Community of West African states, comprises 15 West African countries: Benin, Burkina Faso, Cabo Verde, Côte d'Ivoire, Gambia, Ghana, Guinea, Guinea-Bissau, Liberia, Mali, Niger, Nigeria, Senegal, Sierra Leone and Togo. The overall GIZ project supports the regional dissemination of experience concerning renewable energies and aims at improving the capacities of utilities in the long term.
Output Area B of the project "Generation - RE flagship projects" follows a two-pronged approach:
- Documentation of information on and experience with existing RE flagship projects;
- Support to the development of planned projects through technical assistance for project development and transaction advice, accompanied by documentation of experience.
intec's services
Provision and coordination of a pool of short-term experts to carry out the following tasks:
- Support to ECREEE in the process of screening, evaluating and prioritizing RE projects or promotion schemes
- Support to project developers and government representatives on technical, legal, financial and economic aspects of selected projects.
- Monitoring of selected projects during critical phases of their development and reporting of required action.
- Compilation of experiences with the selected projects and support to ECREEE / other institutions in the region in the dissemination of key findings and lessons learnt.
- Assistance to ECREEE and GIZ in supporting selected ECOWAS member states in creating an enabling legal, regulatory and administrative framework for grid-connected RE projects.
The above tasks cover PV, wind, small hydropower and biomass technology.
Client
ECREEE - ECOWAS Centre for Renewable Energy and Energy EfficiencyFinancing
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbHPeriod of implementation
01.04.2015 - 15.12.2017 -
Uganda - Mutundwe - Entebbe 132 kV Power Transmission Line and Related Substation Works
The project scope comprises the following:
- Construction of approximately 36 km of double circuit 132 kV transmission line between Mutundwe Substation near Kampala City and Entebbe, partly with four circuits and with OPGW on one circuit.
- Extension of the existing 132/33/11 kV Mutundwe Substation (two outgoing 132 kV feeders, extension of busbar system; extension/modification of protection, control, telecommunication, and auxiliary AC/DC power supply systems; civil works).
- Entebbe Substation: Construction of a new outdoor 132/33 kV substation and 33 kV indoor switchgear (double busbar system, two incoming 132 kV line feeders, two 132/33 kV transformer bays with 50 MVA power transformers, one bus coupler bay, protection, control and SCADA, tel-ecommunication and auxiliary power supply equipment, 33 kV indoor switchgear with two incom-ing and six outgoing feeders, a connection by 33 kV underground cable to the existing 33/11 kV distribution; control building, all related civil works).
intec's services
Project Design and Preparation of Tender Documents:
Review of the 2011 feasibility study report; review and adjustment of line route; pegging of angle towers; power system analysis with PSS/E; soil test report and project design report; elaboration of design and technical specifications for transmission line and substations; preparation of tender documents for EPC contracting.
Assistance during the Tendering Stage:
Lead of pre-bid meeting and site visit with Bidders; Bidder's clarifications; bid evaluation; post-tender clarifications; preparation of evaluation report; assistance during contract negotiations; preparation of EPC contracts.Project Management and Construction Supervision:
Review and approval of design calculations and drawings; factory acceptance and site tests; supervision of works on site; monitoring of time schedule; project cost control; processing of contractors' invoices; monitoring of environmental management plan and of the adherence of the social impact assessment recommendations; enforcement of contractor's health; safety and environmental manual; witnessing of commissioning tests; preparation of commissioning protocol; punch list; preparation of final inspection and formal takeover; review of as-built drawings; preparation of project reports.Follow-up during the two-year Defects Liability Period (DLP).
Training of Client's Personnel:
On-the-job training of electrical and civil engineers on power system analysis and design, on the preparation of specifications for transmission lines and substations and on supervision of construction works; elaboration of a detailed training programme and delivery of a 3-week training session for Client's Engineers in the Consultant's home office.
Client
Uganda Electricity Transmission Company Ltd. (UETCL)Financing
Kreditanstalt für Wiederaufbau (KfW)Period of implementation
26.3.2014 - 30.11.2017 -
Mauritania - 50 MW Thermal Power Plant in Zouerate
SNIM (Société Nationale Industrielle et Minière) is a company that extracts the iron ore deposits around the mining city Zouerate, located in the Tiris Zemour region in the north of Mauritania. In order to cover its short-term electricity demand, M/s. SNIM commissioned TRACTEBEL ENGINEERING S.A. to carry out a feasibility study for a 50 MW thermal power plant in the city of Zouerate. The study on the generation units shall evaluate the following two variants:
- Conventional heavy fuel oil-fired generation units
- Dual fuel generation units running on heavy fuel oil and natural gas
Parts of the tasks under this feasibility study have been subcontracted to intec.
intec's services
intec contributed to the following tasks:
Phase 1: Analysis of the SNIM's electricity demand in the short, medium and long term, and definition of a medium and short-term supply strategy
- Site visit and data collection plus assessment of existing studies
- Demand analysis and energy balance
Phase 2: Study of the technology variants and dimensioning of production units (preliminary design)
- Analysis of advantages and disadvantages of each variant
- Proposal for a choice of technology and its justification
- Optimisation of generator unit dimensioning and cost estimates
Phase 3: Feasibility study for the chosen variant
- Site selection and climatic conditions
- Optimisation of nominal capacity of the single production units and determination of principal technical specifications
- Stability and operation analysis of SNIM's electricity network
- Analysis of the project’s technical and economic feasibility
- Environmental and Social Impact Assessment (ESIA)
- Geotechnical survey and laboratory analyses
- Detailed design study and elaboration of tender documents
Client
TRACTEBEL ENGINEERING S.A.Financing
TRACTEBEL ENGINEERING S.A.Period of implementation
08.2013 - 07.2016
ECOWAS Region - Support to RE Flagship Projects
ECOWAS, the Economic Community of West African states, comprises 15 West African countries: Benin, Burkina Faso, Cabo Verde, Côte d'Ivoire, Gambia, Ghana, Guinea, Guinea-Bissau, Liberia, Mali, Niger, Nigeria, Senegal, Sierra Leone and Togo. The overall GIZ project supports the regional dissemination of experience concerning renewable energies and aims at improving the capacities of utilities in the long term.
Output Area B of the project "Generation - RE flagship projects" follows a two-pronged approach:
- Documentation of information on and experience with existing RE flagship projects;
- Support to the development of planned projects through technical assistance for project development and transaction advice, accompanied by documentation of experience.
intec's services
Provision and coordination of a pool of short-term experts to carry out the following tasks:
- Support to ECREEE in the process of screening, evaluating and prioritizing RE projects or promotion schemes
- Support to project developers and government representatives on technical, legal, financial and economic aspects of selected projects.
- Monitoring of selected projects during critical phases of their development and reporting of required action.
- Compilation of experiences with the selected projects and support to ECREEE / other institutions in the region in the dissemination of key findings and lessons learnt.
- Assistance to ECREEE and GIZ in supporting selected ECOWAS member states in creating an enabling legal, regulatory and administrative framework for grid-connected RE projects.
The above tasks cover PV, wind, small hydropower and biomass technology.
Client
ECREEE - ECOWAS Centre for Renewable Energy and Energy EfficiencyFinancing
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbHPeriod of implementation
01.04.2015 - 15.12.2017Uganda - Mutundwe - Entebbe 132 kV Power Transmission Line and Related Substation Works
The project scope comprises the following:
- Construction of approximately 36 km of double circuit 132 kV transmission line between Mutundwe Substation near Kampala City and Entebbe, partly with four circuits and with OPGW on one circuit.
- Extension of the existing 132/33/11 kV Mutundwe Substation (two outgoing 132 kV feeders, extension of busbar system; extension/modification of protection, control, telecommunication, and auxiliary AC/DC power supply systems; civil works).
- Entebbe Substation: Construction of a new outdoor 132/33 kV substation and 33 kV indoor switchgear (double busbar system, two incoming 132 kV line feeders, two 132/33 kV transformer bays with 50 MVA power transformers, one bus coupler bay, protection, control and SCADA, tel-ecommunication and auxiliary power supply equipment, 33 kV indoor switchgear with two incom-ing and six outgoing feeders, a connection by 33 kV underground cable to the existing 33/11 kV distribution; control building, all related civil works).
intec's services
Project Design and Preparation of Tender Documents:
Review of the 2011 feasibility study report; review and adjustment of line route; pegging of angle towers; power system analysis with PSS/E; soil test report and project design report; elaboration of design and technical specifications for transmission line and substations; preparation of tender documents for EPC contracting.
Assistance during the Tendering Stage:
Lead of pre-bid meeting and site visit with Bidders; Bidder's clarifications; bid evaluation; post-tender clarifications; preparation of evaluation report; assistance during contract negotiations; preparation of EPC contracts.
Project Management and Construction Supervision:
Review and approval of design calculations and drawings; factory acceptance and site tests; supervision of works on site; monitoring of time schedule; project cost control; processing of contractors' invoices; monitoring of environmental management plan and of the adherence of the social impact assessment recommendations; enforcement of contractor's health; safety and environmental manual; witnessing of commissioning tests; preparation of commissioning protocol; punch list; preparation of final inspection and formal takeover; review of as-built drawings; preparation of project reports.
Follow-up during the two-year Defects Liability Period (DLP).
Training of Client's Personnel:
On-the-job training of electrical and civil engineers on power system analysis and design, on the preparation of specifications for transmission lines and substations and on supervision of construction works; elaboration of a detailed training programme and delivery of a 3-week training session for Client's Engineers in the Consultant's home office.
Client
Uganda Electricity Transmission Company Ltd. (UETCL)Financing
Kreditanstalt für Wiederaufbau (KfW)Period of implementation
26.3.2014 - 30.11.2017Mauritania - 50 MW Thermal Power Plant in Zouerate
SNIM (Société Nationale Industrielle et Minière) is a company that extracts the iron ore deposits around the mining city Zouerate, located in the Tiris Zemour region in the north of Mauritania. In order to cover its short-term electricity demand, M/s. SNIM commissioned TRACTEBEL ENGINEERING S.A. to carry out a feasibility study for a 50 MW thermal power plant in the city of Zouerate. The study on the generation units shall evaluate the following two variants:
- Conventional heavy fuel oil-fired generation units
- Dual fuel generation units running on heavy fuel oil and natural gas
Parts of the tasks under this feasibility study have been subcontracted to intec.
intec's services
intec contributed to the following tasks:
Phase 1: Analysis of the SNIM's electricity demand in the short, medium and long term, and definition of a medium and short-term supply strategy
- Site visit and data collection plus assessment of existing studies
- Demand analysis and energy balance
Phase 2: Study of the technology variants and dimensioning of production units (preliminary design)
- Analysis of advantages and disadvantages of each variant
- Proposal for a choice of technology and its justification
- Optimisation of generator unit dimensioning and cost estimates
Phase 3: Feasibility study for the chosen variant
- Site selection and climatic conditions
- Optimisation of nominal capacity of the single production units and determination of principal technical specifications
- Stability and operation analysis of SNIM's electricity network
- Analysis of the project’s technical and economic feasibility
- Environmental and Social Impact Assessment (ESIA)
- Geotechnical survey and laboratory analyses
- Detailed design study and elaboration of tender documents