Power distribution systems - Project examples
-
Bangladesh - Project Implementation & Supervision Consultancy Services for the Project “Modernization of Power Distribution – Smart Grids Phase I”
The Project concerns investments to modernize the distribution system in order to contribute to a safer, more reliable and more stable electricity supply as well as to a reduction of greenhouse gas emissions in Bangla-desh.
The targets of the assignment is to provide expertise in the implementation of the following measures:
- Introduction of a central SCADA system to connect 97 nos. 33/11 kV substations of WZPDCL.
- Complete Renovation of 20 (16 Regular type and 4 Rural type) nos. 33/11 kV substations and installation of substations automation system in 8 nos. of additional 33/11 kV substations.
- Construction of 121.68 km and Rehabilitation of 61.60 km of 33 kV distribution lines.
- Construction/Extension of 20 nos. 33kV bays at different WZPDCL’s and PGCB’s substations.
- Bringing WZPDCL's distribution network under GIS mapping.
intec's services
The Consultant’s tasks to be rendered are split into four separate stages and individual steps:
- Preliminary Design and Tender Documents
- Concept review and preparation of Preliminary Design
- Prepare PQ and Tender Documents
- Assistance During Tendering
- Prequalification Process
- Tender Process
- Bid Evaluation Process, Contract Negotiations and Award
- Supervision of Design Works, Construction Works and Supplies
- Contract Implementation
- Commissioning
- Services during Defect Notification Period and Closure of Project
Client
West Zone Power Distribution Company LimitedFinancing
KfWPeriod of implementation
07/2023 - 12/2026 -
Benin - Regional and Cotonou Electrical Distribution Grid Strengthening
The overall purpose of the project is the reinforcement and rehabilitation of the existing electricity distribution system in and around Cotonou and in the regional cities of Parakou, Natitingou, Djougou, and Porto Novo, including conducting the Environmental and Social Assessments (ESIAs) for this work. Works are divided into three activities and include inter alia the following technical measures:
Regional Grid Strengthening Activity:
- New 161 kV infeed including switchgear and transformer, installation of a new 33 kV substation in Natitingou
- Modification and upgrade from 20 to 33 kV of some 120 km of rural OHL connections near Parakou
- Upgrade of existing 161 kV installations and upgrade of some 140 km of rural OHLs and associated transformers from 20 to 33 kV in the Djougou area
- New 63 kV connection, related switchgear modifications, upgrade of some 130 km of rural MV connections from 15 to 33 kV and replacement of associated transformers in the Porto Novo area
- General network improvements
Cotonou Grid Strengthening Activity: new lines, new switchgears, new substations and city network extension (63 kV connections and cable ring, 15 kV and LV connections, new 63 kV switchgear, new transformers 161/63/15 kV, etc.)
National Electricity Dispatch Activity: design and construction of a national distribution control centre and related design activities in the new substations of the other grid strengthening activities.
intec's services
"Base Period": Studies, detailed design, elaboration of tender documents and contract award
- Data collection and establishment of reference studies, basic mapping, revision of network modelling and of load distribution
- Preliminary design, technical specifications and cost estimates
- Elaboration of technical specifications for the tender documents
- Support during tendering and contract award for 6 different lots
"Option A": Design review, construction supervision, testing, commissioning and taking-over
- Supervision of construction works and monitoring of works progress
- Factory acceptance tests, supervision of commissioning and final testing, notification of defects
"Option B": Design and installation of a distribution network data collection system in support of the independent evaluation works and of SBEE's operations
- Identification of data collection needs
- Technical specifications and design of the data collection system
- Installation, capacity building and handingover of the system.
Client
Millennium Challenge Account-Benin II (MCA-Benin II)Financing
Millennium Challenge Corporation (MCC)Period of implementation
12.4.2017 - 12.4.2022 -
Serbia - Supervising Engineer for the Supply and Installation Project "Electrical Equipment for the Reaction in Emergency Situations" in the Republic of Serbia
The purpose of this supervision contract is to provide EPS (Elektroprivreda Srbije) with the necessary assistance in the coordination, supervision, project and site management of three supply contracts.
The technical equipment to be installed under the project includes the following:
- One mobile transformer substation 110/35 kV, 20 MVA (Lot 1)
- Three mobile transformer substations 35/10 kV, 8 MVA (Lot 2)
- One remote monitoring and control system for the MV distribution grid in the area of Elektrosrbija Kraljevo (Lot 3).
intec's services
- Assistance in the preparation of implementation plans and time schedules
- Participation in factory acceptance tests (FATs)
- Assistance in supervising and monitoring construction, commissioning and testing of equipment
- Assistance in project and site management issues, in progress assessment and verification
- Establishment and assistance in QA/QC procedures through witnessing and certification of acceptance testing at site and at the workshops
- Checking and approval of Contractors' payment requests and supporting documents
- Participation in provisional and final acceptance of deliveries and installation
- Preparation of provisional and final acceptance certificates on behalf of the contracting authorities
- Assistance during the defects liability period.
Client
Delegation of the European Union to the Republic of SerbiaFinancing
European UnionPeriod of implementation
29.12.2017 - 28.2.2021
Bangladesh - Project Implementation & Supervision Consultancy Services for the Project “Modernization of Power Distribution – Smart Grids Phase I”
The Project concerns investments to modernize the distribution system in order to contribute to a safer, more reliable and more stable electricity supply as well as to a reduction of greenhouse gas emissions in Bangla-desh.
The targets of the assignment is to provide expertise in the implementation of the following measures:
- Introduction of a central SCADA system to connect 97 nos. 33/11 kV substations of WZPDCL.
- Complete Renovation of 20 (16 Regular type and 4 Rural type) nos. 33/11 kV substations and installation of substations automation system in 8 nos. of additional 33/11 kV substations.
- Construction of 121.68 km and Rehabilitation of 61.60 km of 33 kV distribution lines.
- Construction/Extension of 20 nos. 33kV bays at different WZPDCL’s and PGCB’s substations.
- Bringing WZPDCL's distribution network under GIS mapping.
intec's services
The Consultant’s tasks to be rendered are split into four separate stages and individual steps:
- Preliminary Design and Tender Documents
- Concept review and preparation of Preliminary Design
- Prepare PQ and Tender Documents
- Assistance During Tendering
- Prequalification Process
- Tender Process
- Bid Evaluation Process, Contract Negotiations and Award
- Supervision of Design Works, Construction Works and Supplies
- Contract Implementation
- Commissioning
- Services during Defect Notification Period and Closure of Project
Client
West Zone Power Distribution Company LimitedFinancing
KfWPeriod of implementation
07/2023 - 12/2026Benin - Regional and Cotonou Electrical Distribution Grid Strengthening
The overall purpose of the project is the reinforcement and rehabilitation of the existing electricity distribution system in and around Cotonou and in the regional cities of Parakou, Natitingou, Djougou, and Porto Novo, including conducting the Environmental and Social Assessments (ESIAs) for this work. Works are divided into three activities and include inter alia the following technical measures:
Regional Grid Strengthening Activity:
- New 161 kV infeed including switchgear and transformer, installation of a new 33 kV substation in Natitingou
- Modification and upgrade from 20 to 33 kV of some 120 km of rural OHL connections near Parakou
- Upgrade of existing 161 kV installations and upgrade of some 140 km of rural OHLs and associated transformers from 20 to 33 kV in the Djougou area
- New 63 kV connection, related switchgear modifications, upgrade of some 130 km of rural MV connections from 15 to 33 kV and replacement of associated transformers in the Porto Novo area
- General network improvements
Cotonou Grid Strengthening Activity: new lines, new switchgears, new substations and city network extension (63 kV connections and cable ring, 15 kV and LV connections, new 63 kV switchgear, new transformers 161/63/15 kV, etc.)
National Electricity Dispatch Activity: design and construction of a national distribution control centre and related design activities in the new substations of the other grid strengthening activities.
intec's services
"Base Period": Studies, detailed design, elaboration of tender documents and contract award
- Data collection and establishment of reference studies, basic mapping, revision of network modelling and of load distribution
- Preliminary design, technical specifications and cost estimates
- Elaboration of technical specifications for the tender documents
- Support during tendering and contract award for 6 different lots
"Option A": Design review, construction supervision, testing, commissioning and taking-over
- Supervision of construction works and monitoring of works progress
- Factory acceptance tests, supervision of commissioning and final testing, notification of defects
"Option B": Design and installation of a distribution network data collection system in support of the independent evaluation works and of SBEE's operations
- Identification of data collection needs
- Technical specifications and design of the data collection system
- Installation, capacity building and handingover of the system.
Client
Millennium Challenge Account-Benin II (MCA-Benin II)Financing
Millennium Challenge Corporation (MCC)Period of implementation
12.4.2017 - 12.4.2022Serbia - Supervising Engineer for the Supply and Installation Project "Electrical Equipment for the Reaction in Emergency Situations" in the Republic of Serbia
The purpose of this supervision contract is to provide EPS (Elektroprivreda Srbije) with the necessary assistance in the coordination, supervision, project and site management of three supply contracts.
The technical equipment to be installed under the project includes the following:
- One mobile transformer substation 110/35 kV, 20 MVA (Lot 1)
- Three mobile transformer substations 35/10 kV, 8 MVA (Lot 2)
- One remote monitoring and control system for the MV distribution grid in the area of Elektrosrbija Kraljevo (Lot 3).
intec's services
- Assistance in the preparation of implementation plans and time schedules
- Participation in factory acceptance tests (FATs)
- Assistance in supervising and monitoring construction, commissioning and testing of equipment
- Assistance in project and site management issues, in progress assessment and verification
- Establishment and assistance in QA/QC procedures through witnessing and certification of acceptance testing at site and at the workshops
- Checking and approval of Contractors' payment requests and supporting documents
- Participation in provisional and final acceptance of deliveries and installation
- Preparation of provisional and final acceptance certificates on behalf of the contracting authorities
- Assistance during the defects liability period.
Client
Delegation of the European Union to the Republic of SerbiaFinancing
European UnionPeriod of implementation
29.12.2017 - 28.2.2021-
Ethiopia - Addis Ababa Transmission & Distribution System Rehabilitation & Upgrading Project
An Addis Ababa Distribution Master Plan (AADMP) was elaborated to identify a number of rehabilitation, short-term and medium-term subprojects to be undertaken until 2022 and 2034 respectively. These subprojects are summarised in the ‘Addis Ababa Transmission & Distribution System Rehabilitation & Upgrading Project (AATDRUP)’. They have been allocated into four suitable contract packages.
The present project covers Package-III: Short- and Medium-Term Project (Substation and Transmission), which includes the upgrading of 11 existing substations (7.5/15/33/45 kV), the construction of one new 132/33/15 kV GIS substation, and the construction of a number of 132 kV double-circuit overhead lines, 33 kV feeder lines, and 132 kV underground cables.
intec's services
- Review and finalisation of bidding documents
- Assistance during the bidding period
- Bid evaluation, contract negotiations and preparation of contract documents
- Assistance during procurement
- Design, review, approval, supervision, and quality control of construction works
- Witnessing of factory acceptance tests
- Follow-up of environmental mitigation measures
- Final inspection, issuance of completion certificate and operational acceptance certificate
- Training of the EEP's staff members on-the-job and in the Consultant's home office
- General capacity building and technical assistance
- Project reporting
Client
Ethiopian Electric Power (EEP)Financing
African Development Bank (AfDB)Period of implementation
01.2019 - 01.2021 -
Iraq - German Credit Facility to Assist the Return of IDPs in Iraq (GCFI) – Management and Monitoring Consultant
Rebuilding territories liberated from terrorist activities constitutes a priority to the Iraqi government as part of its overall objective of long-term recovery and stabilisation. The overarching objective of the GCFI is to contribute to the permanent return of internally displaced persons (IDPs) to their home locations in Iraq. To this end, the GCFI will support investments into the restoration of local economic and social infrastructure. The programme will cover interventions in the energy, water/sanitations, roads/bridges, education and health sectors, with an initial focus on energy, water/sanitation and roads/bridges.
Major tasks of the Management and Monitoring Consultant (MC) are:- Support ReFAATO in setting up the programme’s monitoring system
- Capacitate the Project Management Teams (PMT) at the relevant Line Ministries in their role as PIAs, especially prior to the engagement of the GCFI Technical Implementation Consultant (TIC)
Under the programme, intec provides services for the monitoring of investment package implementation in the field of energy, particularly for the following projects:
- Rehabilitation of one 400/132/11 kV, 4 x 250 MVA GIS substation
- Construction of two new 132/33 kV, 3 x 63 MVA GIS substations
- Construction of two new 33/11 kV, 3 x 31.5 MVA distribution substations
- Construction of one new 154 km 132 kV double-circuit transmission line
- Rehabilitation of one 132/33 kV, 3 x 63 MVA GIS substation and three 132/33/11 kV AIS substations
- Supply of three 132/33/11 kV, 3 x 63 MVA power transformers
- Supply of eight 33/11 kV, 31.5 MVA mobile substations, five 33/11 kV, 31.5 MVA power transformers
- Supply of distribution transformers 11/0.4 kV, different power ratings, distribution kiosks and accessories
intec's services
Development of a monitoring system:
- Design financial and technical monitoring systems
- Develop an Environmental and Social Management Framework
- Develop and implement a public information strategy and a grievance redress mechanism
Implementation of monitoring system (throughout Project Implementation)
- Support for overall project monitoring and reporting
- Social and environmental safeguard management, monitoring and safety and security risk management
Capacity building to ReFAATO and the Ministry of Electricity regarding the implementation of the GCFI
Client
ReFAATO – Reconstruction Fund for Areas Affected by Terroristic OperationsFinancing
KfW Development BankPeriod of implementation
12.2017 - 12.2020 -
Nigerian Energy Support Programme (NESP) II
The Nigerian Energy Support Programme (NESP), co-funded by the European Union (EU) and the German government and implemented by GIZ in collaboration with the Federal ministry of Power, Works and Housing (FMPWH), builds upon an initial 4-year phase during which NESP supported, inter alia, regulatory reforms allowing for the integration of variable ER, notably solar, into the grid.; the development of a structured bidding approach for competitive procurement of on-grid solar capacities and to enhance and better grid planning and operations. The programme also supported general policy formulation and sector coordination.
During its second phase, NESP will continue supporting on all these aspects. Additionally, NESP II will support project driven structured bidding approaches in line with government strategies, extend the transmission focus towards the distribution level and will support additional regulatory topics, e.g. with regards to ancillary services
intec's services
- Assistance in leading the further development of the on-grid solar market in Nigeria
- Assistance in the development of new and the enforcement of existing regulation supporting the development of the large scale on-grid solar
- Assistance in the development of studies on grid protection systems and stability
- Assistance in system planning processes that allow for the integration of vRE, notably solar, into the grid.
Client
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbHFinancing
European UnionPeriod of implementation
15.01.2019 - 30.11.2020
Ethiopia - Addis Ababa Transmission & Distribution System Rehabilitation & Upgrading Project
An Addis Ababa Distribution Master Plan (AADMP) was elaborated to identify a number of rehabilitation, short-term and medium-term subprojects to be undertaken until 2022 and 2034 respectively. These subprojects are summarised in the ‘Addis Ababa Transmission & Distribution System Rehabilitation & Upgrading Project (AATDRUP)’. They have been allocated into four suitable contract packages.
The present project covers Package-III: Short- and Medium-Term Project (Substation and Transmission), which includes the upgrading of 11 existing substations (7.5/15/33/45 kV), the construction of one new 132/33/15 kV GIS substation, and the construction of a number of 132 kV double-circuit overhead lines, 33 kV feeder lines, and 132 kV underground cables.
intec's services
- Review and finalisation of bidding documents
- Assistance during the bidding period
- Bid evaluation, contract negotiations and preparation of contract documents
- Assistance during procurement
- Design, review, approval, supervision, and quality control of construction works
- Witnessing of factory acceptance tests
- Follow-up of environmental mitigation measures
- Final inspection, issuance of completion certificate and operational acceptance certificate
- Training of the EEP's staff members on-the-job and in the Consultant's home office
- General capacity building and technical assistance
- Project reporting
Client
Ethiopian Electric Power (EEP)Financing
African Development Bank (AfDB)Period of implementation
01.2019 - 01.2021Iraq - German Credit Facility to Assist the Return of IDPs in Iraq (GCFI) – Management and Monitoring Consultant
Rebuilding territories liberated from terrorist activities constitutes a priority to the Iraqi government as part of its overall objective of long-term recovery and stabilisation. The overarching objective of the GCFI is to contribute to the permanent return of internally displaced persons (IDPs) to their home locations in Iraq. To this end, the GCFI will support investments into the restoration of local economic and social infrastructure. The programme will cover interventions in the energy, water/sanitations, roads/bridges, education and health sectors, with an initial focus on energy, water/sanitation and roads/bridges.
Major tasks of the Management and Monitoring Consultant (MC) are:
- Support ReFAATO in setting up the programme’s monitoring system
- Capacitate the Project Management Teams (PMT) at the relevant Line Ministries in their role as PIAs, especially prior to the engagement of the GCFI Technical Implementation Consultant (TIC)
Under the programme, intec provides services for the monitoring of investment package implementation in the field of energy, particularly for the following projects:
- Rehabilitation of one 400/132/11 kV, 4 x 250 MVA GIS substation
- Construction of two new 132/33 kV, 3 x 63 MVA GIS substations
- Construction of two new 33/11 kV, 3 x 31.5 MVA distribution substations
- Construction of one new 154 km 132 kV double-circuit transmission line
- Rehabilitation of one 132/33 kV, 3 x 63 MVA GIS substation and three 132/33/11 kV AIS substations
- Supply of three 132/33/11 kV, 3 x 63 MVA power transformers
- Supply of eight 33/11 kV, 31.5 MVA mobile substations, five 33/11 kV, 31.5 MVA power transformers
- Supply of distribution transformers 11/0.4 kV, different power ratings, distribution kiosks and accessories
intec's services
Development of a monitoring system:
- Design financial and technical monitoring systems
- Develop an Environmental and Social Management Framework
- Develop and implement a public information strategy and a grievance redress mechanism
Implementation of monitoring system (throughout Project Implementation)
- Support for overall project monitoring and reporting
- Social and environmental safeguard management, monitoring and safety and security risk management
Capacity building to ReFAATO and the Ministry of Electricity regarding the implementation of the GCFI
Client
ReFAATO – Reconstruction Fund for Areas Affected by Terroristic OperationsFinancing
KfW Development BankPeriod of implementation
12.2017 - 12.2020Nigerian Energy Support Programme (NESP) II
The Nigerian Energy Support Programme (NESP), co-funded by the European Union (EU) and the German government and implemented by GIZ in collaboration with the Federal ministry of Power, Works and Housing (FMPWH), builds upon an initial 4-year phase during which NESP supported, inter alia, regulatory reforms allowing for the integration of variable ER, notably solar, into the grid.; the development of a structured bidding approach for competitive procurement of on-grid solar capacities and to enhance and better grid planning and operations. The programme also supported general policy formulation and sector coordination.
During its second phase, NESP will continue supporting on all these aspects. Additionally, NESP II will support project driven structured bidding approaches in line with government strategies, extend the transmission focus towards the distribution level and will support additional regulatory topics, e.g. with regards to ancillary services
intec's services
- Assistance in leading the further development of the on-grid solar market in Nigeria
- Assistance in the development of new and the enforcement of existing regulation supporting the development of the large scale on-grid solar
- Assistance in the development of studies on grid protection systems and stability
- Assistance in system planning processes that allow for the integration of vRE, notably solar, into the grid.
Client
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbHFinancing
European UnionPeriod of implementation
15.01.2019 - 30.11.2020-
Tanzania - Kenya-Tanzania Power Interconnection Project (KTPIP) (Tanzanian Part)
Tanzania and Kenya have joined forces to construct a 400 kV interconnection line that runs from a proposed 400 kV substation at Isinya near Nairobi in Kenya up to Arusha in Tanzania (210 km) and further to a planned 400 kV substation in Singida (300 km). Works in Tanzania are divided into 6 lots as follows:
- Lot T1: 400 kV double circuit OHL between Singida and Babati (approx. 150 km)
- Lot T2: 400 kV double circuit OHL between Babati and Arusha (approx. 150 km)
- Lot T3: 400 kV double circuit OHL between Arusha and the Kenya border (approx. 114 km)
- Lot T4: New 400 kV Arusha substation and extension of the existing 220/33 kV Singida Substation (two additional 220 kV line bays, three breakers and two shunt reactors)
- Lot T5: Rural electrification projects (approx. 80 km of 33 kV lines and low voltage system including customer connections)
- Lot T6: Four new 400 kV substations in the towns of Iringa, Dodoma, Singida and Shinyanga
intec's services
Phase 0: Procurement
- Contract negotiations and preparation of contract documents with the EPC contractors
Phase 1: Pre-Construction
- Review of EPC Contractors' detailed design
- Elaboration of project management manuals
- Function-based definition of applicable standards and project construction guide documents
Phase 2: Construction
- Supervision and quality control of construction works and commissioning
- Monitoring and follow-up of environmental issues and mitigation measures
- Supervision and clarification of project's cultural heritage issues
- Factory test witnessing
- Organisation of joint site meetings
- Reporting
Training of Employer's Staff
- On-the-job training on design approval, construction supervision and project management
- Overseas training for Employer's senior engineers on system planning and network analysis, power system protection and automation, SCADA and telecommunication, power grid operation and maintenance, scheduled and preventive maintenance of HV lines and substations, environmental and social impact assessments (ESIA), resettlement action plans (RAP) and implementation of environmental and social management plans (ESMP)
Client
Tanzania Electric Supply Company Ltd. (TANESCO)Financing
African Development Bank, Japanese International Cooperation AgencyPeriod of implementation
2017 - 2020 -
Kenya - Power Interconnection Project (KTPIP) (Kenyan Part)
Tanzania and Kenya have joined forces to construct a 400 kV interconnection line that runs from a proposed 400 kV substation at Isinya near Nairobi in Kenya up to Arusha in Tanzania (210 km) and further to a planned 400 kV substation in Singida (300 km). Works in Kenya comprise the following:
- Lot K1: Approx. 96 km of 400 kV transmission line between Isinya Substation and the Kenya-Tanzania border.
intec's services
Phase 0: Procurement
- Contract negotiations and preparation of contract documents with the EPC contractors
Phase 1: Pre-Construction
- Review of EPC Contractors' detailed design
- Elaboration of project management manuals
- Function-based definition of applicable standards and project construction guide documents
Phase 2: Construction
- Supervision and quality control of construction works and commissioning
- Monitoring and follow-up of environmental issues and mitigation measures
- Supervision and clarification of project's cultural heritage issues
- Factory test witnessing
- Organisation of joint site meetings
- Reporting
- Support during the 12-months' Defects Liability Period
Training of Employer's Staff
- On-the-job training on design approval, construction supervision and project management
- Overseas' training for Employer's senior engineers on system planning and network analysis, power system protection and automation, SCADA and telecommunication, power grid operation and maintenance, scheduled and preventive maintenance of HV lines and substations, environmental and social impact assessments (ESIA), resettlement action plans (RAP) and implementation of environmental and social management plans (ESMP)
Client
Kenya Electricity Transmission Company Limited (KETRACO)Financing
African Development Bank, Japanese International Cooperation AgencyPeriod of implementation
2017 - 2020 -
Benin - Selection of IPP Consultant and IPP Transaction Advisor
In order to increase the effective installed generating capacity in Benin, a program has been established to attract the participation of Independent Power Producers (IPPs) to develop, design, construct, operate and maintain solar photovoltaic (PV) generation facilities in the country. The program includes the development of an IPP institutional framework and standard forms of contract as well as the execution of a competitive bidding process for GoB.
The selected Consultant will structure and lead the transaction process for GoB as Transaction Advisor. The solar PV sites are located in Natitingou (5 MW), Parakou (15 MW), Djougou (10 MW) and Bohicon (15 MW).
intec's services
- Base Period: Review of legal and institutional arrangements, IPP framework, risk analysis, standard forms of contract (PPA etc.), off-taker and credit enhancement considerations, tariff structure and financial model, competitive IPP solicitation process and training and capacity building;
- Option 1: Addressing technical, environmental and social requirements
- Option 2: Building of network model, steady state studies including load flow and short circuit analysis, dynamic studies including voltage, transient (rotor angle), frequency stability and low voltage ride through;
- Option 3: Advice GoB on all transaction-structuring issues, identification of potential investors, market the IPP transaction opportunity to developers and investors; development of RFP and other solicitation documents,
- Option 4: Providing technical and legal advice through financial close of IPP transaction(s).
Client
Millennium Challenge Account-Benin II (MCA-Benin II)Financing
The United States of America through the Millennium Challenge Corporation (MCC)Period of implementation
04.2018 - 06.2020
Tanzania - Kenya-Tanzania Power Interconnection Project (KTPIP) (Tanzanian Part)
Tanzania and Kenya have joined forces to construct a 400 kV interconnection line that runs from a proposed 400 kV substation at Isinya near Nairobi in Kenya up to Arusha in Tanzania (210 km) and further to a planned 400 kV substation in Singida (300 km). Works in Tanzania are divided into 6 lots as follows:
- Lot T1: 400 kV double circuit OHL between Singida and Babati (approx. 150 km)
- Lot T2: 400 kV double circuit OHL between Babati and Arusha (approx. 150 km)
- Lot T3: 400 kV double circuit OHL between Arusha and the Kenya border (approx. 114 km)
- Lot T4: New 400 kV Arusha substation and extension of the existing 220/33 kV Singida Substation (two additional 220 kV line bays, three breakers and two shunt reactors)
- Lot T5: Rural electrification projects (approx. 80 km of 33 kV lines and low voltage system including customer connections)
- Lot T6: Four new 400 kV substations in the towns of Iringa, Dodoma, Singida and Shinyanga
intec's services
Phase 0: Procurement
- Contract negotiations and preparation of contract documents with the EPC contractors
Phase 1: Pre-Construction
- Review of EPC Contractors' detailed design
- Elaboration of project management manuals
- Function-based definition of applicable standards and project construction guide documents
Phase 2: Construction
- Supervision and quality control of construction works and commissioning
- Monitoring and follow-up of environmental issues and mitigation measures
- Supervision and clarification of project's cultural heritage issues
- Factory test witnessing
- Organisation of joint site meetings
- Reporting
Training of Employer's Staff
- On-the-job training on design approval, construction supervision and project management
- Overseas training for Employer's senior engineers on system planning and network analysis, power system protection and automation, SCADA and telecommunication, power grid operation and maintenance, scheduled and preventive maintenance of HV lines and substations, environmental and social impact assessments (ESIA), resettlement action plans (RAP) and implementation of environmental and social management plans (ESMP)
Client
Tanzania Electric Supply Company Ltd. (TANESCO)Financing
African Development Bank, Japanese International Cooperation AgencyPeriod of implementation
2017 - 2020Kenya - Power Interconnection Project (KTPIP) (Kenyan Part)
Tanzania and Kenya have joined forces to construct a 400 kV interconnection line that runs from a proposed 400 kV substation at Isinya near Nairobi in Kenya up to Arusha in Tanzania (210 km) and further to a planned 400 kV substation in Singida (300 km). Works in Kenya comprise the following:
- Lot K1: Approx. 96 km of 400 kV transmission line between Isinya Substation and the Kenya-Tanzania border.
intec's services
Phase 0: Procurement
- Contract negotiations and preparation of contract documents with the EPC contractors
Phase 1: Pre-Construction
- Review of EPC Contractors' detailed design
- Elaboration of project management manuals
- Function-based definition of applicable standards and project construction guide documents
Phase 2: Construction
- Supervision and quality control of construction works and commissioning
- Monitoring and follow-up of environmental issues and mitigation measures
- Supervision and clarification of project's cultural heritage issues
- Factory test witnessing
- Organisation of joint site meetings
- Reporting
- Support during the 12-months' Defects Liability Period
Training of Employer's Staff
- On-the-job training on design approval, construction supervision and project management
- Overseas' training for Employer's senior engineers on system planning and network analysis, power system protection and automation, SCADA and telecommunication, power grid operation and maintenance, scheduled and preventive maintenance of HV lines and substations, environmental and social impact assessments (ESIA), resettlement action plans (RAP) and implementation of environmental and social management plans (ESMP)
Client
Kenya Electricity Transmission Company Limited (KETRACO)Financing
African Development Bank, Japanese International Cooperation AgencyPeriod of implementation
2017 - 2020Benin - Selection of IPP Consultant and IPP Transaction Advisor
In order to increase the effective installed generating capacity in Benin, a program has been established to attract the participation of Independent Power Producers (IPPs) to develop, design, construct, operate and maintain solar photovoltaic (PV) generation facilities in the country. The program includes the development of an IPP institutional framework and standard forms of contract as well as the execution of a competitive bidding process for GoB.
The selected Consultant will structure and lead the transaction process for GoB as Transaction Advisor. The solar PV sites are located in Natitingou (5 MW), Parakou (15 MW), Djougou (10 MW) and Bohicon (15 MW).
intec's services
- Base Period: Review of legal and institutional arrangements, IPP framework, risk analysis, standard forms of contract (PPA etc.), off-taker and credit enhancement considerations, tariff structure and financial model, competitive IPP solicitation process and training and capacity building;
- Option 1: Addressing technical, environmental and social requirements
- Option 2: Building of network model, steady state studies including load flow and short circuit analysis, dynamic studies including voltage, transient (rotor angle), frequency stability and low voltage ride through;
- Option 3: Advice GoB on all transaction-structuring issues, identification of potential investors, market the IPP transaction opportunity to developers and investors; development of RFP and other solicitation documents,
- Option 4: Providing technical and legal advice through financial close of IPP transaction(s).