HV & EHV grids - Project examples
-
Tanzania - 400 kV Transmission Line Iringa-Shinyanga
The objective of the project was to reinforce the existing 200 kV transmission line from Iringa to Shinyanga by constructing approximately 700 km of 400 kV transmission line and associated facilities.
The Iringa - Shinyanga transmission line is divided into 3 line sections: Iringa - Dodoma (225 km), Dodoma - Singida (227 km), and Singida - Shinyanga (228 km).
The project was carried out for Tanzania Electric Supply Company (TANESCO).
intec's services
- Design review
- Analysis of contract documents
- Design approval
- Calibration of the tower program to the project's design conditions and the Contractor's material characteristics
- Equipment type tests
- Tower type tests
- Factory acceptance tests
- Training on OHL and substation design for the Employer’s personnel.
Financing
SubcontractingPeriod of implementation
12.2013 - 08.2015 -
UAE - 33/11 kV Primary Substations and 22(11)/0.4 kV Distribution Substations (Lots A, B and C)
The project provides consultancy services for the establishment of power supply to medium-size development projects in Abu Dhabi. Services are divided into three lots - A, B, and C, plus a total of four variation orders.
- The work under Lot A covers all services required for the supply and erection of three new 33/11 kV primary substations and related cable circuits including Al-Rahba
- Lot B covers the overview of Developer's designs, bidding process and site construction works for primary and distribution substations (33/11 kV, 22(11)/0.4 kV) and 11 kV switching stations for various Developer projects such as Al Reef Villas, ICAD (M-41), South Shamka, ADNEC, Sowah Island, Saraya development, Zayed Sports City, Danet Abu Dhabi, and Building Material City.
- The services for Lot C comprise full engineering and site supervision for establishing temporary power supply to the projects identified under Lots A and B
- Variation order 1: Additional consultancy services for 33/11 kV primary substations under Lot A
- Variation order 2: Establishment of power supply to a complex with 98 villas in Abu Dhabi (11/0.4 kV substations, 11 kV cables, feeder pillars and LV cables)
- Variation order 3: Consultancy services for the establishment of temporary and permanent power supply to the prestigious Yahsat Satellite Ground Station in Abu Dhabi involving installation, testing and commissioning of 33/11 kV primary substation, 33/11 kV package units, 11/0.4 kV substations, 33 and 11 kV cables
- Variation order 4: Retendering of 33/11 kV primary substation at Al Rahba and inclusion of scope for extension of 11 kV feeder panels in selected 132/11 kV primary substations
intec's services
Lot A:
- Site survey/data collection for the identification of three 33/11 kV primary substations and associated 33 kV cable routes
- Preparation of conceptual design including load flow and voltage drop analysis
- Preparation of tender documents and conducting the entire bidding process including pre-bid clarifications, bid evaluation and preparation of contract documents
- Review and approval of Contractors’ design documents
- Full site supervision of Contractors’ site work including commissioning and issuance of preliminary and final acceptance certificate (PAC & FAC)
- Warranty service
Lot B:
- Review and approval of Developer’s designs for primary and distribution substations and associated cables (2 x 33/11 kV primary substations, 289 x 22/0.4 kV, 107 x 33/11 kV and 11/0.4 kV package units)
- Review and approval of tender documents prepared by the Developers for their scope of work
- Review and approval of Developers' material submittals
- Overview supervision of Developer’s construction work at the site by way of random checks; witnessing all major testing and commissioning activities
Lot C:
- Engineering and full site supervision for establishing the temporary power supply to Developers' sites.
Variation Order 1:
- Additional consultancy services for conception design of 33/11 kV primary substations under Lot A.
Variation Order 2 (98 Villas Project):
- Conceptual study, preliminary design and detailed engineering for 11 kV distribution substation and associated cable routes
- Preparation of tender documentation, bid evaluation and contract documents
- Design review
- Full site supervision and services during the warranty period
Variation Order 3 (Yahsat Satellite Ground Station):
- Design of 33/11 kV package unit with 8.5 km 33 kV cable, one 33/11 kV primary substation and seven 11/0.4 kV distribution substations with associated 11 kV cable worksPreparation of conceptual and final designs for SCADA, telecommunication and telemetry systems and their testing for integration into DMS to meet Smart Grid standards
- Overview of site supervision of the above works including supply, installation, testing, commissioning and energisation
Variation Order 4:
- Re-tendering for the 33/11 kV primary substation at Al Rahba
- Conducting the entire bidding process for the extension of the 11 kV feeder panels.
- Full site supervision of Contractor's site works including commissioning of PAC and FAC
- Warranty services
Client
Abu Dhabi Distribution Company (ADDC)Financing
Abu Dhabi Distribution Company (ADDC)Period of implementation
01.2008 - 01.2015 -
UAE - 400 kV Switching Station at Hameem Junction / Mussafah
The works for the new 400 kV switching station at Hameem Junction were divided into two lots which had the following technical features:
Lot 1: Substation Works, including:
- 400 kV gas-insulated (GIS) switchgear with a double busbar system,
- 6 OHL bays, 2 bus section bays, 2 bus coupler bays, 2 spare OHL bays, 2 spare inter-bus transformer bays, space for two spare feeders,
- power and control cables, control and protection, coordination with the remote ends, interface with the load dispatch centre’s SCADA system, and communication works,
- fire-fighting systems, air conditioning, and civil works.
Lot 2: 200 kV Overhead Line Works, including:
- Loop-in and loop-out of the 400 kV d.c. lines from Madinat Zayed, Mussafah, AASW/Taweelah B,
- Line route survey, soil investigations, and access roads,
- Design, supply and installation of foundations,
- Design, supply, erection and painting of towers and gantries
- Supply and installation of insulators, conductors, and OPGW,
- Installation of an aircraft warning system.
intec's services
- Data collection and site survey,
- Preparation of preliminary and final design,
- Elaboration of costs and budget,
- Preparation of tender documents and evaluation of bids,
- Site supervision during the construction period,
- Testing,
- Site supervision during the warranty period.
Client
Abu Dhabi Transmission and Despatch Company (TRANSCO)Financing
TRANSCOPeriod of implementation
05.2008 - 12.2012
Tanzania - 400 kV Transmission Line Iringa-Shinyanga
The objective of the project was to reinforce the existing 200 kV transmission line from Iringa to Shinyanga by constructing approximately 700 km of 400 kV transmission line and associated facilities.
The Iringa - Shinyanga transmission line is divided into 3 line sections: Iringa - Dodoma (225 km), Dodoma - Singida (227 km), and Singida - Shinyanga (228 km).
The project was carried out for Tanzania Electric Supply Company (TANESCO).
intec's services
- Design review
- Analysis of contract documents
- Design approval
- Calibration of the tower program to the project's design conditions and the Contractor's material characteristics
- Equipment type tests
- Tower type tests
- Factory acceptance tests
- Training on OHL and substation design for the Employer’s personnel.
Financing
SubcontractingPeriod of implementation
12.2013 - 08.2015UAE - 33/11 kV Primary Substations and 22(11)/0.4 kV Distribution Substations (Lots A, B and C)
The project provides consultancy services for the establishment of power supply to medium-size development projects in Abu Dhabi. Services are divided into three lots - A, B, and C, plus a total of four variation orders.
- The work under Lot A covers all services required for the supply and erection of three new 33/11 kV primary substations and related cable circuits including Al-Rahba
- Lot B covers the overview of Developer's designs, bidding process and site construction works for primary and distribution substations (33/11 kV, 22(11)/0.4 kV) and 11 kV switching stations for various Developer projects such as Al Reef Villas, ICAD (M-41), South Shamka, ADNEC, Sowah Island, Saraya development, Zayed Sports City, Danet Abu Dhabi, and Building Material City.
- The services for Lot C comprise full engineering and site supervision for establishing temporary power supply to the projects identified under Lots A and B
- Variation order 1: Additional consultancy services for 33/11 kV primary substations under Lot A
- Variation order 2: Establishment of power supply to a complex with 98 villas in Abu Dhabi (11/0.4 kV substations, 11 kV cables, feeder pillars and LV cables)
- Variation order 3: Consultancy services for the establishment of temporary and permanent power supply to the prestigious Yahsat Satellite Ground Station in Abu Dhabi involving installation, testing and commissioning of 33/11 kV primary substation, 33/11 kV package units, 11/0.4 kV substations, 33 and 11 kV cables
- Variation order 4: Retendering of 33/11 kV primary substation at Al Rahba and inclusion of scope for extension of 11 kV feeder panels in selected 132/11 kV primary substations
intec's services
Lot A:
- Site survey/data collection for the identification of three 33/11 kV primary substations and associated 33 kV cable routes
- Preparation of conceptual design including load flow and voltage drop analysis
- Preparation of tender documents and conducting the entire bidding process including pre-bid clarifications, bid evaluation and preparation of contract documents
- Review and approval of Contractors’ design documents
- Full site supervision of Contractors’ site work including commissioning and issuance of preliminary and final acceptance certificate (PAC & FAC)
- Warranty service
Lot B:
- Review and approval of Developer’s designs for primary and distribution substations and associated cables (2 x 33/11 kV primary substations, 289 x 22/0.4 kV, 107 x 33/11 kV and 11/0.4 kV package units)
- Review and approval of tender documents prepared by the Developers for their scope of work
- Review and approval of Developers' material submittals
- Overview supervision of Developer’s construction work at the site by way of random checks; witnessing all major testing and commissioning activities
Lot C:
- Engineering and full site supervision for establishing the temporary power supply to Developers' sites.
Variation Order 1:
- Additional consultancy services for conception design of 33/11 kV primary substations under Lot A.
Variation Order 2 (98 Villas Project):
- Conceptual study, preliminary design and detailed engineering for 11 kV distribution substation and associated cable routes
- Preparation of tender documentation, bid evaluation and contract documents
- Design review
- Full site supervision and services during the warranty period
Variation Order 3 (Yahsat Satellite Ground Station):
- Design of 33/11 kV package unit with 8.5 km 33 kV cable, one 33/11 kV primary substation and seven 11/0.4 kV distribution substations with associated 11 kV cable worksPreparation of conceptual and final designs for SCADA, telecommunication and telemetry systems and their testing for integration into DMS to meet Smart Grid standards
- Overview of site supervision of the above works including supply, installation, testing, commissioning and energisation
Variation Order 4:
- Re-tendering for the 33/11 kV primary substation at Al Rahba
- Conducting the entire bidding process for the extension of the 11 kV feeder panels.
- Full site supervision of Contractor's site works including commissioning of PAC and FAC
- Warranty services
Client
Abu Dhabi Distribution Company (ADDC)Financing
Abu Dhabi Distribution Company (ADDC)Period of implementation
01.2008 - 01.2015UAE - 400 kV Switching Station at Hameem Junction / Mussafah
The works for the new 400 kV switching station at Hameem Junction were divided into two lots which had the following technical features:
Lot 1: Substation Works, including:
- 400 kV gas-insulated (GIS) switchgear with a double busbar system,
- 6 OHL bays, 2 bus section bays, 2 bus coupler bays, 2 spare OHL bays, 2 spare inter-bus transformer bays, space for two spare feeders,
- power and control cables, control and protection, coordination with the remote ends, interface with the load dispatch centre’s SCADA system, and communication works,
- fire-fighting systems, air conditioning, and civil works.
Lot 2: 200 kV Overhead Line Works, including:
- Loop-in and loop-out of the 400 kV d.c. lines from Madinat Zayed, Mussafah, AASW/Taweelah B,
- Line route survey, soil investigations, and access roads,
- Design, supply and installation of foundations,
- Design, supply, erection and painting of towers and gantries
- Supply and installation of insulators, conductors, and OPGW,
- Installation of an aircraft warning system.
intec's services
- Data collection and site survey,
- Preparation of preliminary and final design,
- Elaboration of costs and budget,
- Preparation of tender documents and evaluation of bids,
- Site supervision during the construction period,
- Testing,
- Site supervision during the warranty period.
Client
Abu Dhabi Transmission and Despatch Company (TRANSCO)Financing
TRANSCOPeriod of implementation
05.2008 - 12.2012-
Bangladesh - Project "Western Grid Network Development Project, WGNDP"
Bangladesh expressed as main goal "electricity to all by 2021". With support from German Financial Cooperation through KfW, PGCB launched a feasibility study on the "Transmission System Improvement, Western Zone", in the framework of which tender documents were prepared for the following technical measures, packaged into 6 lots:
- 230 kV double-circuit transmission lines (new construction, line-in/line-out), in total 81.5 km
- 132 kV transmission lines, double- and single circuit (new construction, line-in/line-out, reconductoring, second circuit stringing), in total 242 km
- 132/33 kV substations (new construction (3), bay extensions (8))
- new construction of two 230/132 kV substations.
intec's services
Project Implementation Consultant (PIC), i.e.:
- Contracts management and administration, coordination between PGCB and Contractors
- Review and approval of design
- Random checks on FAT, and support during factory inspection and acceptance testing
- Progress monitoring on site
- Monitoring and supervision of the Contractors' environmental and social (E&S) management
- Payment certification
- Participation in and support for site testing, commissioning and handing-over
- Support during the defects liability period
- Training
- Record keeping and reporting.
Client
Power Grid Company of Bangladesh Ltd. (PGCB)Financing
Kreditanstalt für Wiederaufbau (KfWPeriod of implementation
7.3.2018 - 6.7.2021 -
UAE - Establishment of Power Supply to Yas Island
In order to sustain the development of different regions of Abu Dhabi Island, ADDC, in collaboration with private developers, initiated several projects to expand the electrical network by adding primary substations and integrating them into the existing power network. Among other projects, the private developer ALDAR Properties PJSC embarked on the development of Yas Island to develop it into a major touristic, residential and commercial city located in the suburbs of Abu Dhabi Island.
Accordingly, a project was initiated to provide consulting services for the network expansion projects, both for temporary and permanent power supply, with the aim to assure the compliance of the installations with ADDC's / ADWEA's design guidelines, specifications and the overall project schedule.
intec's services
Stage 1:
- Review and approval of the Developer's 33 kV design
- Identification of 33 kV cable routes including their coordination with the town planning department
- Review and approval of Developer's tender documents and bid evaluation/recommendations
- Review and approval of material submitted by the Developer
- Review of progress reporting
Stage 2:
- As above, but for the 22 kV and the LV level.
Stage 3:
- Field supervision (overview) of construction works at the Developer's site
- Inspection of site works to ensure compliance with ADDC's requirements
- Verification of quantities and related documents / drawings to be handed over to ADDC
- Review of progress reporting.
Client
Abu Dhabi Distribution Company (ADDC)Financing
Abu Dhabi Distribution Company (ADDC)Period of implementation
02.2008 - 06.2012 -
UAE - 11 kV Feeder Panels in some 132/11 kV Primary Substations in Abu Dhabi Island
22 (twenty two) 132/11 kV primary substations exist in Abu Dhabi Island. In line with ADDC's standards, the number of 11 kV outgoing feeder panels per substation is 48 (forty eight). This standard design was adopted from the year 2005. However, most of the primaries commissioned prior to 2005 have less than 48 (forty eight) 11 kV outgoing feeders.
With the objective to install additional 11 kV outgoing feeder panels, ADWEA commissioned a study on 12 selected existing 132/11 kV primary substations in Abu Dhabi Island and the implementation of the recommendations for network augmentation at these substations.
The scope of these consultancy services included study, design, preparation of tender documents, tendering and supervision of the supply, the installation and the commissioning of 11 kV outgoing feeder panels at some of the above primary substations. The aim was to utilize the available spare FIRM capacity to serve new customers / connections, to reinforce the existing network and also provide panels for connecting the battery energy storage system (BESS).
intec's services
- Site survey for 12 (twelve) 132/11 kV primary substations;
- Submission of site survey report to ADWEA for approval;
- Submission of scope of work (SoW) and bills of quantities (BoQ) to ADWEA for approval;
Client
Abu Dhabi Water & Electricity Authority (ADWEA)Financing
Abu Dhabi Water & Electricity Authority (ADWEA)Period of implementation
06.2009 - 11.2010
Bangladesh - Project "Western Grid Network Development Project, WGNDP"
Bangladesh expressed as main goal "electricity to all by 2021". With support from German Financial Cooperation through KfW, PGCB launched a feasibility study on the "Transmission System Improvement, Western Zone", in the framework of which tender documents were prepared for the following technical measures, packaged into 6 lots:
- 230 kV double-circuit transmission lines (new construction, line-in/line-out), in total 81.5 km
- 132 kV transmission lines, double- and single circuit (new construction, line-in/line-out, reconductoring, second circuit stringing), in total 242 km
- 132/33 kV substations (new construction (3), bay extensions (8))
- new construction of two 230/132 kV substations.
intec's services
Project Implementation Consultant (PIC), i.e.:
- Contracts management and administration, coordination between PGCB and Contractors
- Review and approval of design
- Random checks on FAT, and support during factory inspection and acceptance testing
- Progress monitoring on site
- Monitoring and supervision of the Contractors' environmental and social (E&S) management
- Payment certification
- Participation in and support for site testing, commissioning and handing-over
- Support during the defects liability period
- Training
- Record keeping and reporting.
Client
Power Grid Company of Bangladesh Ltd. (PGCB)Financing
Kreditanstalt für Wiederaufbau (KfWPeriod of implementation
7.3.2018 - 6.7.2021UAE - Establishment of Power Supply to Yas Island
In order to sustain the development of different regions of Abu Dhabi Island, ADDC, in collaboration with private developers, initiated several projects to expand the electrical network by adding primary substations and integrating them into the existing power network. Among other projects, the private developer ALDAR Properties PJSC embarked on the development of Yas Island to develop it into a major touristic, residential and commercial city located in the suburbs of Abu Dhabi Island.
Accordingly, a project was initiated to provide consulting services for the network expansion projects, both for temporary and permanent power supply, with the aim to assure the compliance of the installations with ADDC's / ADWEA's design guidelines, specifications and the overall project schedule.
intec's services
Stage 1:
- Review and approval of the Developer's 33 kV design
- Identification of 33 kV cable routes including their coordination with the town planning department
- Review and approval of Developer's tender documents and bid evaluation/recommendations
- Review and approval of material submitted by the Developer
- Review of progress reporting
Stage 2:
- As above, but for the 22 kV and the LV level.
Stage 3:
- Field supervision (overview) of construction works at the Developer's site
- Inspection of site works to ensure compliance with ADDC's requirements
- Verification of quantities and related documents / drawings to be handed over to ADDC
- Review of progress reporting.
Client
Abu Dhabi Distribution Company (ADDC)Financing
Abu Dhabi Distribution Company (ADDC)Period of implementation
02.2008 - 06.2012UAE - 11 kV Feeder Panels in some 132/11 kV Primary Substations in Abu Dhabi Island
22 (twenty two) 132/11 kV primary substations exist in Abu Dhabi Island. In line with ADDC's standards, the number of 11 kV outgoing feeder panels per substation is 48 (forty eight). This standard design was adopted from the year 2005. However, most of the primaries commissioned prior to 2005 have less than 48 (forty eight) 11 kV outgoing feeders.
With the objective to install additional 11 kV outgoing feeder panels, ADWEA commissioned a study on 12 selected existing 132/11 kV primary substations in Abu Dhabi Island and the implementation of the recommendations for network augmentation at these substations.
The scope of these consultancy services included study, design, preparation of tender documents, tendering and supervision of the supply, the installation and the commissioning of 11 kV outgoing feeder panels at some of the above primary substations. The aim was to utilize the available spare FIRM capacity to serve new customers / connections, to reinforce the existing network and also provide panels for connecting the battery energy storage system (BESS).
intec's services
- Site survey for 12 (twelve) 132/11 kV primary substations;
- Submission of site survey report to ADWEA for approval;
- Submission of scope of work (SoW) and bills of quantities (BoQ) to ADWEA for approval;