UAE - 11 kV Power Distribution Network Design (Tawazun Industrial Park - TIP)
![865 UAE](/sites/default/files/styles/project/public/2018-11/IMG_2741.jpg?itok=nWu7JcIA)
Tawazun Industrial Parkis in process for developing 11KV Substation and Cabling works in TIP which involves:
- Supply and Installation of 1500 KVA Package Substation including LV Panels and 11 KV Cablings - 4 to 7 nos based on Load Study.
- Supply and Installation of 3000KVA Substation Including LV Panels and 11KV Cablings - 1 nos
intec's services
Consultancy Services for 11 kV Power Distribution Network Design - 11/0.415 kV Distribution Substations and its associated 11 kV cabling works, 11 kV power supply loop cabling work between Primary Substation and IGT building at Tawazun Industrial Park (TIP), Abu Dhabi
Stage 1 covering:
- Load demand study
- Protection study (Upstream & Downstream)
- LDN development and submission to TIP
- Tender designs
Stage 2 covering:
- Development of tender documents
- Tendering support and Contractor’s Contract documentation covering pre- and post-bid clarifications and Technical & Commercial tender evaluation
Stage 3: Site Supervision
Client
Tawazun Industrial Park (TIP)
Financing
Tawazun Industrial Park (TIP)
Period of implementation
01.03.2018 - 30.05.2019